| Trade & Classification | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR Building ASBE0002-002 | $46.50 | $29.43 | $75.93 |
| BOILERMAKER Building BOIL0667-005 | $47.13 | $28.93 | $76.06 |
| BRICKLAYER Brick Refractory/Brick Placement Worker Building BRWV0015-009 | $32.64 | $23.95 | $56.59 |
| BRICKLAYER Bricklayer & Brick Pointer/Caulker/Cleaner Building BRWV0015-008 | $31.70 | $25.93 | $57.63 |
| CARPENTER Building CARP0436-005 (Including Batt Insulation, Form Work and Scaffold Builder) | $30.51 | $26.05 | $56.56 |
| CARPENTER Building SUWV2012-048 (Drywall Hanging Only) | $23.23 | $12.13 | $35.36 |
| CEMENT MASON/CONCRETE FINISHER Building PLAS0926-002 Scope differs by code/WD | $30.38 | $22.87 | $53.25 |
| CEMENT MASON/CONCRETE FINISHER Building PLAS0926-005 Scope differs by code/WD | $30.38 | $22.87 | $53.25 |
| ELECTRICIAN Building ELEC0141-010 | $39.25 | $31.23 | $70.48 |
| GLAZIER Building PAIN1195-002 | $32.89 | $13.38 | $46.27 |
| Group 2 Building LABO0379-015 | $24.94 | $16.20 | $41.14 |
| Group 3 Building LABO0379-015 | $24.94 | $16.20 | $41.14 |
| Group 4 Building LABO0379-015 | $24.94 | $16.20 | $41.14 |
| IRONWORKER Building IRON0549-009 (Ornamental, Reinforcing, Sheeting and Structural) | $35.19 | $25.66 | $60.85 |
| LABORER Building LABO1149-010 Scope differs by code/WD | $25.92 | $16.88 | $42.80 |
| LABORER Building SUWV2012-048 (Wacker Roller Operator) | $23.07 | $11.07 | $34.14 |
| LABORER Group 1 Building LABO0379-015 | $24.94 | $16.20 | $41.14 |
| MASON - STONE Building BRWV0015-010 | $33.00 | $26.18 | $59.18 |
| MILLWRIGHT Building CARP0443-009 | $37.40 | $26.06 | $63.46 |
| OPERATOR: Backhoe Building SUWV2012-048 | $21.51 | $7.36 | $28.87 |
| OPERATOR: Roller Building SUWV2012-048 | $25.24 | $16.15 | $41.39 |
| PAINTER Building PAIN0091-012 (Brush, Roller and Spray) | $29.47 | $18.72 | $48.19 |
| PAINTER Building PAIN0970-007 (Drywall Finishing/Taping) | $30.57 | $20.06 | $50.63 |
| PIPEFITTER, Includes HVAC Pipe Installation Building SUWV2012-048 | $25.32 | $19.97 | $45.29 |
| PLASTERER Building PLAS0926-005 (EIFS and Fireproofing) | $30.50 | $22.22 | $52.72 |
| PLUMBER Building PLUM0083-006 | $38.04 | $39.72 | $77.76 |
| POWER EQUIPMENT OPERATOR: GROUP 1 Building ENGI0132-012 | $46.56 | $22.05 | $68.61 |
| POWER EQUIPMENT OPERATOR: GROUP 2 Building ENGI0132-012 | $46.21 | $22.05 | $68.26 |
| POWER EQUIPMENT OPERATOR: GROUP 3 Building ENGI0132-012 | $45.21 | $22.05 | $67.26 |
| POWER EQUIPMENT OPERATOR: GROUP 4 Building ENGI0132-012 | $34.71 | $22.05 | $56.76 |
| ROOFER Building ROOF0188-003 | $34.00 | $19.11 | $53.11 |
| SHEET METAL WORKER Building SHEE0033-003 (Includes HVAC Duct Installation) | $34.92 | $29.70 | $64.62 |
| TILE FINISHER Building BRWV0015-014 | $27.00 | $22.57 | $49.57 |
| TILE SETTER Building BRWV0009-007 | $31.65 | $25.56 | $57.21 |
| Truck drivers: GROUP 2 Building TEAM0175-005 | $29.81 | $22.50 | $52.31 |
| Truck drivers: GROUP 3 Building TEAM0175-005 | $29.96 | $22.50 | $52.46 |