HI20260001 rev 3
Hawaii, Honolulu, Kalawao, Kauai, Maui · Building, Heavy, Highway, Residential
| Trade | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKERS/INSULATOR | 46.90 | 29.75 | 76.65 |
| BOILERMAKER | 49.37 | 31.25 | 80.62 |
| BRICKLAYER: POINTERS, CAULKERS AND WEATHERPROOFERS | 48.28 | 32.23 | 80.51 |
| BRICKLAYERS AND STONEMASONS | 48.03 | 32.23 | 80.26 |
| TILE, MARBLE & TERRAZZO WORKER | 44.69 | 33.00 | 77.69 |
| TILE, MARBLE & TERRAZZO WORKER | 43.14 | 33.00 | 76.14 |
| TILE, MARBLE & TERRAZZO WORKER | 46.50 | 33.00 | 79.50 |
| CARPENTERS: | 55.50 | 29.81 | 85.31 |
| CARPENTERS: MILLWRIGHTS AND MACHINE ERECTORS | 55.75 | 29.81 | 85.56 |
| CARPENTERS: POWER SAW OPERATORS (2 H.P. AND OVER) | 55.65 | 29.81 | 85.46 |
| DRYWALL AND ACOUSTICAL WORKERS AND LATHERS | 55.75 | 29.81 | 85.56 |
| ELECTRICIANS | 56.55 | 33.16 | 89.71 |
| ELECTRICIANS: CABLE SPLICERS | 63.90 | 33.38 | 97.28 |
| ELECTRICIANS: TELECOMMUNICATION WORKER | 41.00 | 16.28 | 57.28 |
| LINE CONSTRUCTION: CABLE SPLICERS | 63.90 | 33.38 | 97.28 |
| LINE CONSTRUCTION: GROUNDMEN/TRUCK DRIVERS | 42.41 | 27.14 | 69.55 |
| LINE CONSTRUCTION: HEAVY EQUIPMENT OPERATORS | 50.90 | 30.75 | 81.65 |
| LINE CONSTRUCTION: LINEMEN | 56.55 | 33.16 | 89.71 |
| LINE CONSTRUCTION: TELECOMMUNICATION WORKER | 41.00 | 16.28 | 57.28 |
| DIVER TENDER: OTHER THAN AQUA LUNG | 59.94 | 35.68 | 95.62 |
| DIVER: (AQUA LUNG) (SCUBA) (over 30 feet) | 81.72 | 35.68 | 117.40 |
| DIVER: (AQUA LUNG) (SCUBA) (up to 30 feet) | 72.35 | 35.68 | 108.03 |
| DIVER: OTHER THAN AQUA LUNG | 81.72 | 35.68 | 117.40 |
| HELICOPTER WORK, AIRBORNE HOIST OPERATOR FOR HELIC… | 61.52 | 35.68 | 97.20 |
| HELICOPTER WORK: CO-PILOT OF HELICOPTER | 61.66 | 35.68 | 97.34 |
| HELICOPTER WORK: PILOT OF HELICOPTER | 62.83 | 35.68 | 98.51 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 1: F… | 57.96 | 35.68 | 93.64 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 2: C… | 58.07 | 35.68 | 93.75 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 4: B… | 58.51 | 35.68 | 94.19 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 5: A… | 58.82 | 35.68 | 94.50 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 6: B… | 59.47 | 35.68 | 95.15 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 7: C… | 59.79 | 35.68 | 95.47 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 8: A… | 59.90 | 35.68 | 95.58 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 9: C… | 60.01 | 35.68 | 95.69 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 9A: … | 60.24 | 35.68 | 95.92 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 10: … | 60.30 | 35.68 | 95.98 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 10A:… | 60.45 | 35.68 | 96.13 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 11: … | 60.60 | 35.68 | 96.28 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 12: … | 60.96 | 35.68 | 96.64 |
| POWER EQUIPMENT OPERATOR - TUNNEL WORK, GROUP 12A:… | 61.32 | 35.68 | 97.00 |
| POWER EQUIPMENT OPERATORS:, GROUP 1: FORK LIFT | 57.66 | 35.68 | 93.34 |
| POWER EQUIPMENT OPERATORS:, GROUP 2: CONVEYOR OPER… | 57.77 | 35.68 | 93.45 |
| POWER EQUIPMENT OPERATORS:, GROUP 4: BOOM TRUCK OR… | 58.21 | 35.68 | 93.89 |
| POWER EQUIPMENT OPERATORS:, GROUP 5: ASPHALT PLANT… | 58.52 | 35.68 | 94.20 |
| POWER EQUIPMENT OPERATORS:, GROUP 6: BOOM TRUCK OR… | 59.17 | 35.68 | 94.85 |
| POWER EQUIPMENT OPERATORS:, GROUP 7: CRUSHER PLANT… | 59.49 | 35.68 | 95.17 |
| POWER EQUIPMENT OPERATORS:, GROUP 8: ASPHALT PLANT… | 59.60 | 35.68 | 95.28 |
| POWER EQUIPMENT OPERATORS:, GROUP 9: COMBINATION M… | 59.71 | 35.68 | 95.39 |
| POWER EQUIPMENT OPERATORS:, GROUP 9A: DOZER | 59.94 | 35.68 | 95.62 |
| POWER EQUIPMENT OPERATORS:, GROUP 10: CHICAGO BOOM… | 60.00 | 35.68 | 95.68 |
| POWER EQUIPMENT OPERATORS:, GROUP 10A: BOAT OPERAT… | 60.15 | 35.68 | 95.83 |
| POWER EQUIPMENT OPERATORS:, GROUP 11: AUTOMATIC SL… | 60.30 | 35.68 | 95.98 |
| POWER EQUIPMENT OPERATORS:, GROUP 12 CLAMSHELL OR … | 60.66 | 35.68 | 96.34 |
| POWER EQUIPMENT OPERATORS:, GROUP 12A: DOZER | 61.02 | 35.68 | 96.70 |
| POWER EQUIPMENT OPERATORS:, GROUP 13: TRUCK DRIVER | 57.94 | 35.68 | 93.62 |
| POWER EQUIPMENT OPERATORS:, GROUP 13A: DUMP TRUCK,… | 58.21 | 35.68 | 93.89 |
| POWER EQUIPMENT OPERATORS:, GROUP 13B: WATER TRUCK | 58.52 | 35.68 | 94.20 |
| POWER EQUIPMENT OPERATORS:, GROUP 13C: TRUCK DRIVE… | 59.17 | 35.68 | 94.85 |
| POWER EQUIPMENT OPERATORS:, GROUP 13D: TRUCK DRIVE… | 59.49 | 35.68 | 95.17 |
| POWER EQUIPMENT OPERATORS:, GROUP 13E: END DUMPS, … | 59.60 | 35.68 | 95.28 |
| STAND-BY DIVER: (AQUA LUNG) (SCUBA) | 62.97 | 35.68 | 98.65 |
| STAND-BY DIVER: OTHER THAN AQUA LUNG | 62.97 | 35.68 | 98.65 |
| DREDGING (BOAT OPERATORS): BOAT DECKHAND | 57.94 | 35.68 | 93.62 |
| DREDGING (BOAT OPERATORS): BOAT OPERATOR | 60.15 | 35.68 | 95.83 |
| DREDGING (BOAT OPERATORS): MASTER BOAT OPERATOR | 60.30 | 35.68 | 95.98 |
| DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 1: … | 60.66 | 35.68 | 96.34 |
| DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 2: … | 60.00 | 35.68 | 95.68 |
| DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 3: … | 59.60 | 35.68 | 95.28 |
| DREDGING:, CLAMSHELL OR DIPPER DREDGING: GROUP 4: … | 57.94 | 35.68 | 93.62 |
| DREDGING:, DERRICKS: GROUP 1: OPERATORS | 60.66 | 35.68 | 96.34 |
| DREDGING:, DERRICKS: GROUP 2: SAURMAN TYPE DRAGLIN… | 60.00 | 35.68 | 95.68 |
| DREDGING:, DERRICKS: GROUP 3: DECKMATE; SAURMAN TY… | 59.60 | 35.68 | 95.28 |
| DREDGING:, DERRICKS: GROUP 4: DECKHAND, FIREMAN, O… | 57.94 | 35.68 | 93.62 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 1: LEV… | 60.30 | 35.68 | 95.98 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 2: WAT… | 60.15 | 35.68 | 95.83 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 3: MEC… | 60.00 | 35.68 | 95.68 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 4: DOZ… | 59.94 | 35.68 | 95.62 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 5: DEC… | 59.60 | 35.68 | 95.28 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 6: WIN… | 59.49 | 35.68 | 95.17 |
| DREDGING:, HYDRAULIC SUCTION DREDGES: GROUP 7: DEC… | 57.94 | 35.68 | 93.62 |
| POWER EQUIPMENT OPERATORS | 58.67 | 34.86 | 93.53 |
| POWER EQUIPMENT OPERATORS | 59.07 | 34.86 | 93.93 |
| POWER EQUIPMENT OPERATORS (PAVING): ASPHALT RAKER | 57.68 | 34.86 | 92.54 |
| POWER EQUIPMENT OPERATORS | 59.16 | 34.86 | 94.02 |
| POWER EQUIPMENT OPERATORS (PAVING): COLD PLANER | 59.47 | 34.86 | 94.33 |
| POWER EQUIPMENT OPERATORS | 57.68 | 34.86 | 92.54 |
| POWER EQUIPMENT OPERATORS | 56.70 | 34.86 | 91.56 |
| POWER EQUIPMENT OPERATORS | 58.64 | 34.86 | 93.50 |
| POWER EQUIPMENT OPERATORS (PAVING): GRADER | 59.47 | 34.86 | 94.33 |
| POWER EQUIPMENT OPERATORS | 57.18 | 34.86 | 92.04 |
| POWER EQUIPMENT OPERATORS | 58.64 | 34.86 | 93.50 |
| POWER EQUIPMENT OPERATORS | 58.96 | 34.86 | 93.82 |
| POWER EQUIPMENT OPERATORS | 57.41 | 34.86 | 92.27 |
| POWER EQUIPMENT OPERATORS | 58.84 | 34.86 | 93.70 |
| POWER EQUIPMENT OPERATORS (PAVING): SCREED PERSON | 58.64 | 34.86 | 93.50 |
| POWER EQUIPMENT OPERATORS (PAVING): SOIL STABILIZE… | 59.47 | 34.86 | 94.33 |
| IRONWORKERS A. EMPLOYEES WILL BE PAID $.50 PER HOU… | 50.50 | 43.46 | 93.96 |
| LABORERS: DRILLER | 44.75 | 25.96 | 70.71 |
| LABORERS: FINAL CLEAN UP | 31.40 | 21.37 | 52.77 |
| LABORERS: GUNITE/SHOTCRETE OPERATOR AND HIGH SCALE… | 42.25 | 25.96 | 68.21 |
| LABORERS: MASON TENDER/HOD CARRIER | 42.25 | 25.96 | 68.21 |
| LABORERS: POWDERMAN | 42.75 | 25.96 | 68.71 |
| LABORERS: WINDOW WASHER (BOSUN CHAIR) | 41.25 | 25.96 | 67.21 |
| SEE LABORERS: LABORER I IN FOOTER | 41.75 | 25.96 | 67.71 |
| SEE LABORERS: LABORER II IN FOOTER | 39.15 | 25.96 | 65.11 |
| UNDERGROUND LABORER, GROUP 1: WATCHMEN; CHANGE HOU… | 42.35 | 25.91 | 68.26 |
| UNDERGROUND LABORER, GROUP 2: SWAMPER; BRAKEMAN; B… | 43.85 | 25.91 | 69.76 |
| UNDERGROUND LABORER, GROUP 3: CHUCKTENDERS AND CAB… | 44.35 | 25.91 | 70.26 |
| UNDERGROUND LABORER, GROUP 4: MINERS - TUNNEL | 45.35 | 25.91 | 71.26 |
| UNDERGROUND LABORER, GROUP 5: SHAFT WORK & RAISE | 45.70 | 25.91 | 71.61 |
| UNDERGROUND LABORER, GROUP 6: SHIFTER | 45.95 | 25.91 | 71.86 |
| UNDERGROUND LABORER, GROUP 7: SHIFTER | 46.40 | 25.91 | 72.31 |
| PAINTERS: BRUSH | 44.05 | 30.05 | 74.10 |
| PAINTERS: SANDBLASTER; SPRAY | 44.05 | 30.05 | 74.10 |
| GLAZIERS | 48.50 | 40.20 | 88.70 |
| SOFT FLOOR LAYERS | 43.27 | 35.18 | 78.45 |
| TAPER | 47.36 | 32.00 | 79.36 |
| PLASTERER | 46.12 | 34.53 | 80.65 |
| CEMENT MASONS | 44.12 | 33.63 | 77.75 |
| CEMENT MASONS: TROWEL MACHINE OPERATORS | 44.27 | 33.63 | 77.90 |
| PLUMBER, PIPEFITTER, STEAMFITTER & SPRINKLER FITTE… | 53.83 | 33.19 | 87.02 |
| ROOFERS | 43.15 | 21.21 | 64.36 |
| SHEET METAL WORKER | 50.16 | 33.32 | 83.48 |
| DRAPERY INSTALLER | 13.60 | 1.20 | 14.80 |
| FENCE ERECTOR (CHAIN LINK FENCE) | 9.33 | 1.65 | 10.98 |