ID20260044

Heavy

Davis-Bacon Act general wage determination for heavy construction in Idaho.

Modification 2, revised 05/18/2026 25 trade rates 1 county View on SAM.gov

Track ID20260044

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

CARP0808-009 Effective 06/01/2025
Trade Rate Fringe Total
CARPENTER: EXCLUDES FORM WORK (ADAMS, BEAR LAKE, BINGHAM, BOISE, BUTTE, BONNEVILLE, CAMAS, CARIBOU, CASSIA, CLARK, CUSTER, ELMORE, FRANKLIN, FREMONT, GEM, GOODING, IDAHO (SOUTH OF THE 46TH PARALLEL), JEFFERSON, JEROME, LEMHI, LINCOLN, MADISON, MINIDOKA, ONEIDA, OWYHEE, PAYETTE, POWER, TETON, TWIN FALLS, VALLEY AND WASHINGTON COUNTIES) ZONE PAY: ZONE 1 0-30 MILES: FREE ZONE 2 MORE THAN 30-60 MILES: $2.00/PER HOUR ZONE 3 MORE THAN 60 MILES: $3.00/PER HOUR IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE $35.68 $18.24 $53.92
ELEC0449-004 Effective 12/01/2025
Trade Rate Fringe Total
ELECTRICIAN $40.00 $18.74 $58.74
ENGI0370-032 Effective 01/01/2025
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: GROUP 8 BULLDOZER, SCRAPER (OVER 80 YDS TO 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE $37.58 $16.10 $53.68
POWER EQUIPMENT OPERATOR: GROUP 7: DRILL (BIT 8 IN AND OVER), HEAVY DUTY MECHANIC, SCRAPERS (OVER 40 YDS TO 60 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE $37.35 $16.10 $53.45
POWER EQUIPMENT OPERATOR: GROUP 6 DRILLING (BIT UNDER 8IN), OILER, SCRAPER (UP TO AND INCLUDING 40 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE $36.98 $16.10 $53.08
POWER EQUIPMENT OPERATOR: GROUP 10 SCRAPER (OVER 100 YDS) ZONE PAY: ZONE 1 0 - 30 MILES: FREE ZONE 2 30 - 60 MILES: $30.00/PER DAY ZONE 3 MORE THAN 60 MILES: $35.00/PER DAY. IF A PROJECT IS LOCATED IN MORE THAN ONE ZONE THE LOWER ZONE RATE SHALL APPLY ZONES SHALL BE MEASURED FROM THE THE FOLLOWING U.S. POST OFFICES: BOISE: 304 N. 8TH STREET TWIN FALLS: 253 2ND AVE. WEST POCATELLO: CLARK STREET IDAHO FALLS: 875 NORTH CAPITAL AVE $38.06 $16.10 $54.16
IRON0732-003 Effective 06/01/2024
Trade Rate Fringe Total
IRONWORKER, STRUCTURAL $33.37 $22.98 $56.35
LABO0155-008 Effective 01/01/2025
Trade Rate Fringe Total
LABORER: GROUP 3 ASPHALT INCLUDING RAKER, SHOVELER, SPREADER, AND DISTRIBUTOR $33.83 $16.50 $50.33
LABORER: GROUP 1 FLAGGER $33.63 $16.50 $50.13
SUID2010-037 Effective 08/08/2012
Trade Rate Fringe Total
WATER & SEWER LINES: OPERATOR - EXCAVATOR $22.07 $0.00 $22.07
TRUCK DRIVER: WATER TRUCK $24.57 $11.22 $35.79
TRUCK DRIVER: LOWBOY TRUCK $21.00 $12.10 $33.10
TRUCK DRIVER: DUMP TRUCK $17.53 $0.00 $17.53
OPERATOR: CONCRETE BATCH PLANT $24.94 $11.96 $36.90
OPERATOR: LOADER (FRONT END) $21.33 $4.25 $25.58
OPERATOR: GRADER/BLADE $24.91 $8.79 $33.70
OPERATOR: FORKLIFT $17.00 $0.00 $17.00
OPERATOR: CRANE $24.30 $8.38 $32.68
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $21.05 $0.00 $21.05
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $21.15 $6.14 $27.29
LABORER: PIPELAYER $18.23 $3.77 $22.00
LABORER: COMMON OR GENERAL $20.26 $10.15 $30.41
IRONWORKER, REINFORCING $27.22 $16.70 $43.92
CEMENT MASON/CONCRETE FINISHER $18.02 $0.00 $18.02
CARPENTER (FORM WORK ONLY) $25.27 $9.10 $34.37

Modification History

Modification Publication Date
1 01/30/2026
2 05/18/2026

Counties Covered

This wage determination applies to 1 county in Idaho.

Get notified when ID20260044 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.