MT20260056
BuildingDavis-Bacon Act general wage determination for building construction in Montana.
Track MT20260056
Get an email when this wage determination gets a new modification.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Wage Rates
Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.
ASBE0082-002 Effective 08/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| HEAT AND FROST INSULATOR | $43.81 | $21.87 | $65.68 |
BOIL0011-002 Effective 01/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $38.75 | $32.31 | $71.06 |
BRMT0010-001 Effective 06/01/2020 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER | $30.55 | $15.75 | $46.30 |
ELEC0532-006 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN | $43.92 | $18.17 | $62.09 |
ENGI0400-003 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR: (7) CRANES, 150 TONS TO INCLUDING 250 TONS (ADD $1.00 FOR EVERY 100 TONS OVER 250 TONS); CRANE, TOWER (ALL) ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $42.00 | $16.20 | $58.20 |
| POWER EQUIPMENT OPERATOR: (6) CRANES 75 TO 144 TONS, WHIRLEY CRANES ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $40.00 | $16.20 | $56.20 |
| POWER EQUIPMENT OPERATOR: (5) CRANES 45-74 TONS ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $38.00 | $16.20 | $54.20 |
| POWER EQUIPMENT OPERATOR: (4) CRANES 25-44 TONS ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $38.00 | $16.20 | $54.20 |
| POWER EQUIPMENT OPERATOR: (1) A-FRAME TRUCK CRANE ZONE DEFINITIONS FOR POWER EQUPMENT OPERATORS: THE ZONE HOURLY RATES APPLICABLE TO EACH PROJECT SHALL BE DETERMINED BY MEASURING THE ROAD MILES OVER THE SHORTEST PRACTICAL MAINTAINED ROUTE FROM THE NEAREST COUNTY COURT HOUSE OF THE FOLLOWING LISTED TOWNS TO THE CENTER OF THE JOB: BILLINGS, BOZEMAN, BUTTE, GREAT FALLS, HELENA, KALISPELL, MISSOULA ZONE 1: 0 TO 30 MILES - BASE PAY ZONE 2: 30 TO 60 MILES - BASE PAY + $3.50 ZONE 3: OVER 60 MILES - BASE PAY + $5.50 | $21.51 | $16.20 | $37.71 |
IRON0732-014 Effective 06/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER, REINFORCING | $36.83 | $25.30 | $62.13 |
PLUM0030-005 Effective 09/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER/PIPEFITTER (Excluding HVAC Pipe Installation) | $44.35 | $21.87 | $66.22 |
SHEE0103-009 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) | $40.00 | $22.07 | $62.07 |
SUMT2011-032 Effective 01/04/2011 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: DUMP TRUCK | $18.88 | $4.66 | $23.54 |
| ROOFER | $17.36 | $3.83 | $21.19 |
| PLUMBER (HVAC PIPE INSTALLATION) | $25.75 | $10.87 | $36.62 |
| PAINTER: BRUSH, ROLLER AND SPRAY | $19.18 | $0.00 | $19.18 |
| OPERATOR: FORKLIFT | $21.44 | $8.05 | $29.49 |
| OPERATOR: EXCAVATOR | $22.98 | $5.57 | $28.55 |
| LABORER: MASON TENDER - BRICK | $18.37 | $5.94 | $24.31 |
| LABORER: COMMON OR GENERAL | $14.47 | $3.11 | $17.58 |
| IRONWORKER, STRUCTURAL | $20.45 | $12.76 | $33.21 |
| CEMENT MASON/CONCRETE FINISHER | $18.27 | $1.50 | $19.77 |
| CARPENTER, EXCLUDES DRYWALL HANGING, AND FORM WORK | $16.70 | $2.31 | $19.01 |
| CARPENTER (DRYWALL HANGING ONLY) | $22.69 | $0.00 | $22.69 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 0 | 01/02/2026 |
| 1 | 05/18/2026 |
Counties Covered
This wage determination applies to 2 counties in Montana.
Get notified when MT20260056 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.