NJ20260025
BuildingDavis-Bacon Act general wage determination for building construction in New Jersey.
Track NJ20260025
Get an email when this wage determination gets a new modification.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Wage Rates
Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.
ASBE0089-004 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR (includes the application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems; also, the application of firestopping material to openings and penetrations in walls, floors, ceilings and curtain walls; also, all lead PAID HOLIDAYS: The last day prior to the Christmas and New Year's Day observed holiday: 4 hrs. pay | $55.80 | $40.80 | $96.60 |
BRNJ0002-013 Effective 05/01/2021 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| Work on high stacks: 22% per hour additional | $45.20 | $33.26 | $78.46 |
BRNJ0007-012 Effective 07/07/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MARBLE SETTER | $64.66 | $40.97 | $105.63 |
BRNJ0007-013 Effective 06/02/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TERRAZZO FINISHER | $43.63 | $32.12 | $75.75 |
BRNJ0007-017 Effective 06/02/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TILE SETTER | $52.31 | $38.01 | $90.32 |
CARP0006-009 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (SCAFFOLD The first sixty feet at the regular rate, 10% per hour additional for each additional fifty feet thereafter | $57.42 | $34.17 | $91.59 |
CARP0006-010 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER, INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORMWORK, BATT AND BLOWN INSULATION | $57.42 | $34.17 | $91.59 |
CARP0029-006 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SOFT FLOOR LAYER | $57.42 | $34.17 | $91.59 |
CARP0715-007 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MILLWRIGHT | $58.84 | $35.06 | $93.90 |
ELEC0351-009 Effective 09/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN: TELEDATA TECHNICIANS: 15 VOICE DATA LINES OR LESS | $41.00 | $32.75 | $73.75 |
| ELECTRICIAN: TELEDATA TECHNICIANS: 16 VOICE DATA LINES OR MORE AND FIBER OPTICS | $41.00 | $32.75 | $73.75 |
ELEC0351-011 Effective 09/30/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN AND CABLE SPLICER | $55.05 | $48.76 | $103.81 |
| ELECTRICIAN: CABLE SPLICER ON LEAD CABLE | $46.51 | $34.39 | $80.90 |
ENGI0825-017 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: GROUP 4 BOBCAT/SKID LOADER; COMPRESSOR (SINGLE); FARM TRACTOR; FRONT END LOADER (UNDER 1 CU. YD.); HYDROSEEDER; ROLLER, GRADE; PUMP, HYDRAULIC HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $56.59 | $37.50 | $94.09 |
| POWER EQUIPMENT OPERATORS: GROUP 3 ASPHALT SPREADER; BULLDOZER;COMPRESSOR (2 OR 3) (IN BATTERY) (WITHIN 100 FT.); FORKLIFT; FRONT END LOADER (1 CU. YD. AND OVER BUT LESS THAN 2 CU. YD.); LULL; MAN LIFT/OUTSIDE ELEVATOR; MECHANIC; PAVER, ASPHALT; ROLLER, BLACKTOP; TRACTOR; HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $58.22 | $37.50 | $95.72 |
| SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: POWER EQUIPMENT OPERATORS: GROUP 2 BACKHOE LOADER COMBO; CONCRETE PUMPER; GRADER/BLADE (FINISH); HOIST; HYDRAULIC CRANE, 10 TONS AND UNDER; FRONT END LOADER (2 CU. YD. BUT LESS THAN 5 CU. YD.); WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $60.13 | $37.50 | $97.63 |
| SCRAPER; SIDE BOOM HAZARDOUS WASTE REMOVAL WORK: POWER EQUIPMENT OPERATORS: GROUP 1 BACKHOE, INCLUDING BACKHOE TRACK; BOOM; CONCRETE PAVING MACHINE; CRANE (ALL TYPES, INCLUDING OVERHEAD AND STRADDLE TRAVELING TYPE); DRILL (DOWN-THE-HOLE DRILL, ROTARY DRILL, SELF-PROPELLED HYDRAULIC DRILL, SELF-POWERED DRILL); ELEVATING GRADER; EXCAVATOR; FRONT END LOADER (5 CU. YD. AND OVER); PILEDRIVER (LENGTH OF BOOM, INCLUDING LENGTH OF LEADS, SHALL DETERMINE PREMIUM RATE APPLICABLE); TRENCHER HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $61.72 | $37.50 | $99.22 |
ENGI0825-018 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS:, STEEL ERECTION: (GROUP 2) ALL CRANES WITH BOOM INCLUDING JIB, LESS THAN 140 FT. HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $68.58 | $37.50 | $106.08 |
| POWER EQUIPMENT OPERATORS:, STEEL ERECTION: (GROUP 1) ALL CRANES WITH BOOM INCLUDING JIB, 140 FT. AND OVER. HAZARDOUS WASTE REMOVAL WORK: WORK ON A STATE OR FEDERALLY DESIGNATED HAZARDOUS WASTE SITE, WHERE THE WORKER IS IN DIRECT CONTACT WITH HAZARDOUS MATERIAL, AND WHEN PERSONAL PROTECTIVE EQUIPMENT IS REQUIRED FOR RESPIRATORY, SKIN AND EYE PROTECTION: 20% PER HOUR ADDITIONAL. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY OBSERVED, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY; PROVIDED 1) THAT THE WORKER WORKS THREE OF THE PRECEDING FIVE WORK DAYS BEFORE THE HOLIDAY; OR, THE WORK DAY BEFORE THE HOLIDAY AND THE WORK DAY AFTER THE HOLIDAY; AND, 2) THAT THE WORKER WORKS THE WORK DAY BEFORE AND THE WORK DAY AFTER THE HOLIDAY | $70.24 | $37.50 | $107.74 |
IRON0399-011 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER: REINFORCING | $53.24 | $38.40 | $91.64 |
| IRONWORKER: STRUCTURAL AND ORNAMENTAL | $54.24 | $38.40 | $92.64 |
LABO0077-002 Effective 05/01/2022 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER: MASON TENDER: BRICK/CEMENT/CONCRETE | $36.50 | $30.22 | $66.72 |
PAIN0021-035 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| GLAZIER Work at 30 ft. above the working surface, or on a swing stage: $1.00 per hour additional | $49.96 | $35.11 | $85.07 |
PAIN0711-018 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| DRYWALL FINISHER/TAPER | $44.87 | $30.15 | $75.02 |
PAIN0711-019 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PAINTER (BRUSH & ROLLER) | $45.55 | $29.86 | $75.41 |
| PAINTER (SPRAY) | $45.55 | $29.86 | $75.41 |
PLAS0008-007 Effective 05/01/2021 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLASTERER | $38.37 | $31.64 | $70.01 |
PLAS0592-036 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CEMENT MASON/CONCRETE FINISHER | $53.21 | $33.42 | $86.63 |
PLUM0322-009 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER (EXCLUDING HVAC PIPE INSTALLATION) | $56.30 | $50.76 | $107.06 |
| PIPEFITTER (INCLUDING HVAC PIPE INSTALLATION) | $56.30 | $50.76 | $107.06 |
SFNJ0669-006 Effective 04/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SPRINKLER FITTER (FIRE SPRINKLERS) | $59.19 | $36.51 | $95.70 |
SHEE0027-009 Effective 06/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL WORKER (INCLUDING HVAC DUCT INSTALLATION) | $59.08 | $47.06 | $106.14 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 0 | 01/02/2026 |
| 1 | 05/18/2026 |
Counties Covered
This wage determination applies to 1 county in New Jersey.
Get notified when NJ20260025 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.