NY20260006

HeavyHighway

Davis-Bacon Act general wage determination for heavy, highway construction in New York.

Modification 1, revised 05/18/2026 39 trade rates 2 counties View on SAM.gov

Track NY20260006

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

BRNY0002-013 Effective 06/01/2018
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER. FOOTNOTE: A. PAID HOLIDAYS: MEMORIAL DAY, JULY THE 4TH, LABOR DAY, AND THANKSGIVING DAY (PROVIDED THE EMPLOYEE IS EMPLOYED (1) DAY BEFORE AND (1) DAY AFTER THE HOLIDAY $37.23 $19.51 $56.74
CARP0291-006 Effective 07/01/2024
Trade Rate Fringe Total
CARPENTER: CARPENTER (HEAVY & HIGHWAY CONSTRUCTION) $41.03 $24.50 $65.53
ELEC0910-001 Effective 04/01/2025
Trade Rate Fringe Total
ELECTRICIAN $43.50 $28.38 $71.88
ELEC1249-004 Effective 05/05/2025
Trade Rate Fringe Total
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins $61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) $61.56 $36.21 $97.77
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) $49.25 $31.15 $80.40
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab $55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) $55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) $55.40 $31.78 $87.18
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) $35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) $35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) $35.34 $30.12 $65.46
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) $64.59 $42.92 $107.51
ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) $63.14 $33.82 $96.96
ENGI0158-027 Effective 07/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATORS: GROUP 3 $51.42 $32.45 $83.87
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 7 MASTER MECHANIC FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $57.01 $32.45 $89.46
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 6 CRANES 49 TONS AND BELOW FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $57.90 $32.45 $90.35
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 5 CRANES 50 TONS AND OVER FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $59.40 $32.45 $91.85
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 4 TOWER CRANES FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $60.90 $32.45 $93.35
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 2 ASPHALT PAVER, BACKHOE (TRACTOR MOUNTED, RUBBER TIRED), BITUMINOUS RECYCLER MACHINE, BITUMINOUS SPREADER AND MIXER, BLACKTOP PLANT (NONAUTOMATED), BLAST OR ROTARY DRILL (TRUCK OR TRACTOR MOUNTED), BORING MACHINE, CAGE HOIST, CENTRAL MIX PLANT (NONAUTOMATED) AND ALL CONCRETE BATCHING PLANTS, CHERRY PICKER (5 TONS CAPACITY AND UNDER), CONCRETE PAVER (OVER 16S), CRAWLER DRILL, SELF-CONTAINED, CRUSHER, DIESEL POWER UNIT, DRILL RIGS, TRACTOR MOUNTED, FRONT END LOADER (UNDER 4 CU. YD.), GREASEMAN/LUBRICATION ENGINEER, HIPRESSURE BOILER (15 LBS. AND OVER), HOIST (ONE DRUM), HYDRO-AXE, KOLMAN PLANT LOADER AND SIMILAR TYPE LOADERS, L.C.M. WORK BOAT OPERATOR, LOCOMOTIVE MIXER (FOR STABILIZED BASE SELFPROPELLED), MONORAIL MACHINE, PLANT ENGINEER, PROFILER (105 H.P. AND UNDER), GRINDER, POST HOLE DIGGER AND POST DRIVER, POWER BROOM (TOWED), POWER HEATERMAN, POWER SWEEPER, REVINIUS WIDENER, ROLLER (GRADE AND FILL), SCARIFIER, RIDE-ON, SHELL WINDER, SKID STEER LOADER (BOBCAT OR SIMILAR), SPAN-SAW, RIDE-ON, STEAM CLEANER, PUG MILL, PUMP CRETE READY MIX CONCRETE PLANT REFRIGERATION EQUIPMENT (FOR SOIL STABILIZATION)ROAD WIDENER, ROLLER (ALL ABOVE SUBGRADE), SEA MULE, SELF-CONTAINED RIDE-ON ROCK DRILL, EXCLUDING AIR-TRACK TYPE DRILL, SKIDDER, TRACTOR WITH DOZER AND/OR PUSHER, TRENCHER. TUGGER HOIST, VERMEER SAW (RIDE ON, ANY SIZE OR TYPE), WINCH, WINCH CAT FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $53.99 $32.45 $86.44
POWER EQUIPMENT OPERATORS (HEAVY & HIGHWAY): GROUP 1 ASPHALT CURB MACHINE, SELF PROPELLED, SLIPFORM, AUTOMATED CONCRETE SPREADER (CMI TYPE), AUTOMATIC FINE GRADER, BACKHOE (EXCEPT TRACTOR MOUNTED, RUBBER TIRED), BACKHOE EXCAVATOR FULL SWING (CAT 212 OR SIMILAR TYPE), BACK FILLING MACHINE, BELT PLACER (CMI TYPE), BLACKTOP PLANT (AUTOMATED), BOOM TRUCK , CABLEWAY, CAISSON AUGER, CENTRAL MIX CONCRETE PLANT (AUTOMATED), CONCRETE CURB MACHINE, SELF PROPELLED, SLIPFORM, CONCRETE PUMP, CRANE, CHERRY PICKER, DERRICKS (STEEL ERECTION), DRAGLINE, OVERHEAD CRANE (GANTRY OR STRADDLE TYPE), PILE DRIVER, TRUCK CRANE, DIRECTIONAL DRILLING MACHINE, DREDGE, DUAL DRUM PAVER, EXCAVATOR (ALL PURPOSE HYDRAULICALLY OPERATED) (GRADALL OR SIMILAR), FRONT END LOADER ( 4 CU. YD. AND OVER), HEAD TOWER (SAUERMAN OR EQUAL), HOIST (TWO OR THREE DRUM), HOLLAND LOADER, MAINTENANCE ENGINEER, MINE HOIST, MUCKING MACHINE OR MOLE PAVEMENT BREAKER(SP) WERTGEN; PB-4 AND SIMILAR TYPE, POWER GRADER, PROFILER (OVER 105 H.P.) QUAD 9, QUARRY MASTER (OR EQUIVALENT), SCRAPER, FIREMAN, FORM TAMPER, GROUT PUMP, GUNITE MACHINE, HAMMERS (HYDRAULIC SELF-PROPELLED), HYDRA-SPIKER, RIDE-ON, HYDRAULIC PUMP (JACKING SYSTEM), HYDRO-BLASTER (WATER), MULCHING MACHINE, OILER, PARAPET CONCRETE OR PAVEMENT, SHOVEL, SIDE BOOM, SLIP FORM PAVER, TRACTOR DRAWN, BELTTYPE LOADER, TRUCK OR TRAILER MOUNTED LOG , CHIPPER (SELF FEEDER), TUG OPERATOR (MANNED RENTED EQUIPMENT EXCLUDED), TUNNEL SHOVEL MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, AND CHRISTMAS DAY $54.90 $32.45 $87.35
IRON0012-002 Effective 07/01/2024
Trade Rate Fringe Total
IRONWORKERS: (STRUCTURAL, ORNAMENTAL, MACHINERY MOVER & RIGGERS, FENCE ERECTOR, REINFORCING, STONE DERRICKMAN, WELDER) $38.50 $25.48 $63.98
IRONWORKERS: (SHEETER) $38.75 $25.48 $64.23
LABO1822-001 Effective 07/01/2023
Trade Rate Fringe Total
LABORERS: GROUP 3 ALL ROCK OR DRILLING MACHINE OPERATORS (EXCEPT QUARRY MASTER AND SIMILAR TYPE) ACETYLENE TORCH OPERATOR, ASPHALT RAKER, POWDERMAN. HEAVY & HIGHWAY FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $31.47 $27.80 $59.27
PAIN0201-002 Effective 05/01/2025
Trade Rate Fringe Total
PAINTERS: PAINTERS, DRYWALL FINISHERS, SPRAY (ZONE #3 ALL OF CLINTON COUNTY) $33.50 $21.69 $55.19
PAINTERS: PAINTERS, DRYWALL FINISHERS, SPRAY (ZONE #2 ALL OF ESSEX COUNTY) $33.50 $21.69 $55.19
PAINTERS: LEAD ABTATEMENT WORKERS, STRUCTURAL STEEL (ZONE #3 ALL OF CLINTON COUNTY) $34.50 $21.69 $56.19
PAINTERS: LEAD ABATEMENT WORKERS, STRUCTURAL STEEL (ZONE #2 ALL OF ESSEX COUNTY) $34.50 $21.69 $56.19
PAIN0806-003 Effective 10/01/2024
Trade Rate Fringe Total
PAINTERS: STRUCTURAL STEEL AND BRIDGE (CLINTON AND ESSEX COUNTIES) $56.25 $55.14 $111.39
PLUM0773-001 Effective 05/01/2025
Trade Rate Fringe Total
PLUMBER AND STEAMFITTER (ESSEX COUNTY) $45.88 $33.60 $79.48
PLUMBER AND STEAMFITTER (CLINTON COUNTY) $44.88 $33.60 $78.48
TEAM0687-003 Effective 07/01/2025
Trade Rate Fringe Total
TRUCK DRIVERS: GROUP 2: (HEAVY & HIGHWAY CONSTRUCTION) SPECIALIZED EARTH MOVING EQUIPMENT - EUCLID TYPE OR SIMILAR OFF-HIGHWAY EQUIPMENT, WHERE NOT SELF-LOADED, STRADDLE (ROSS) CARRIER, SELF-CONTAINED CONCRETE UNIT, OFF HIGHWAY TANDEM BACK DUMP, TWIN ENGINE EQUIPMENT AND DOUBLE HITCHED EQUIPMENT WHERE NOT SELF LOADED FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY $35.03 $27.02 $62.05
TRUCK DRIVERS: GROUP 1: (HEAVY & HIGHWAY CONSTRUCTION) PICK-UPS, PANEL TRUCKS, FLATBOY MATERIALS TRUCKS (STRAIGHT JOBS), SINGLE AXLE DUMP TRUCKS, DUMPSTERS AND RECEIVERS, GREASERS, TRUCK TIREMAN, PARTS CHASER, TANDEMS AND BATCH TRUCKS, MECHANICS, SEMI TRAILER, LOWBOY TRUCKS, ASPHALT DISTRIBUTOR TRUCKS AND AGITATOR, MIXER TRUCKS AND DUMPCRETE TYPE VEHICLES, TRUCK MECHANIC, FUEL TRUCK AND BUS FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, THANKSGIVING DAY, CHRISTMAS DAY, PROVIDED THE EMPLOYEE HAS WORKED THE DAY BEFORE AND THE DAY AFTER THE HOLIDAY $34.81 $27.02 $61.83

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 2 counties in New York.

Get notified when NY20260006 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.