Wage Rates
Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.
ASBE0091-001 Effective 06/02/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| INSULATOR/ASBESTOS WORKER (INCLUDES APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS) | $46.62 | $49.30 | $95.92 |
| HAZARDOUS MATERIAL HANDLER (DUTIES LIMITED TO PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS WHETHER THEY CONTAIN ASBESTOS OR NOT FROM MECHANICAL SYSTEMS) | $46.62 | $49.30 | $95.92 |
BRNY0001-003 Effective 06/01/2018 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POINTER, CLEANER AND CAULKER | $41.96 | $33.38 | $75.34 |
BRNY0004-001 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MARBLE MASON | $63.92 | $40.20 | $104.12 |
BRNY0005-004 Effective 06/01/2023 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER, CEMENT MASON, PLASTERER & STONEMASON: BRICKLAYERS, CEMENT MASONS, PLASTERERS, STONE MASONS (BUILDING CONSTRUCTION) | $46.39 | $37.45 | $83.84 |
BRNY0007-001 Effective 12/02/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TERRAZZO WORKER/SETTER | $64.62 | $37.63 | $102.25 |
| TERRAZZO FINISHER | $49.59 | $34.25 | $83.84 |
BRNY0007-002 Effective 12/02/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TILE FINISHER | $49.59 | $34.25 | $83.84 |
BRNY0020-001 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MARBLE FINISHER | $49.99 | $37.54 | $87.53 |
BRNY0024-001 Effective 06/03/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER (MARBLE POLISHERS) | $52.32 | $36.25 | $88.57 |
BRNY0052-001 Effective 06/03/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TILE LAYER | $64.40 | $37.13 | $101.53 |
CARP0279-002 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTERS: (HEAVY & HIGHWAY) | $50.12 | $31.73 | $81.85 |
| CARPENTERS (BUILDING) | $50.12 | $31.73 | $81.85 |
CARP0740-001 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MILLWRIGHT | $60.83 | $58.03 | $118.86 |
CARP1556-006 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| DOCK BUILDER & PILEDRIVERMEN | $60.59 | $55.84 | $116.43 |
CARP1556-007 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| DIVER TENDER | $55.00 | $55.84 | $110.84 |
| DIVER | $75.46 | $55.84 | $131.30 |
CARP2287-002 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (SOFT FLOOR LAYERS) | $44.69 | $38.17 | $82.86 |
ELEC0363-003 Effective 04/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (PUTNAM COUNTY) FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY, PRESIDENT'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, PRESIDENTIAL ELECTION DAY, VETERAN'S DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING, CHRISTMAS DAY | $51.50 | $42.22 | $93.72 |
ELEC1249-004 Effective 05/05/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Substation:) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: MECHANIC (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable ins | $61.56 | $36.21 | $97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: LINEMAN & TECHNICIAN (Substation:) | $61.56 | $36.21 | $97.77 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Substation:) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (TRACTOR TRAILER UNIT) (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installat | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN TRUCK DRIVER (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $49.25 | $31.15 | $80.40 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cab | $55.40 | $31.78 | $87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Substation:) | $55.40 | $31.78 | $87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: GROUNDMAN DIGGING MACHINE OPERATOR (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $55.40 | $31.78 | $87.18 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $35.34 | $30.12 | $65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Substation:) | $35.34 | $30.12 | $65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: FLAGMAN (Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :) | $35.34 | $30.12 | $65.46 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Switching structures; railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation) | $64.59 | $42.92 | $107.51 |
| ELECTRICIAN, LINE CONSTRUCTION: CABLE SPLICER (Substation:) | $63.14 | $33.82 | $96.96 |
ENGI0137-003 Effective 03/04/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: GROUP 6 (BUILDING CONSTRUCTION) WAREHOUSE MAN NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $49.26 | $31.32 | $80.58 |
| POWER EQUIPMENT OPERATORS: GROUP 5-B (BUILDING CONSTRUCTION) UTILITY MAN NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $47.00 | $31.32 | $78.32 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A (BUILDING CONSTRUCTION) MASTER MECHANIC NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $61.95 | $31.32 | $93.27 |
| POWER EQUIPMENT OPERATORS: GROUP 5 (BUILDING CONSTRUCTION) MOTORIZED ROLLER (WALK BEHIND) PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $49.53 | $31.32 | $80.85 |
| POWER EQUIPMENT OPERATORS: GROUP 4-B (BUILDING CONSTRUCTION) COMPRESSOR TO 125 FEET; DUST; DUST COLLECTOR; HEATER ALL TYPES; PUMP; PUMP STATION (WATER AND SEWER); STEAM JENNY; SWEEPER; CHIPPER; MULCHER. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $45.94 | $31.32 | $77.26 |
| POWER EQUIPMENT OPERATORS: GROUP 4-A (BUILDING CONSTRUCTION) AIR TRACTOR DRILL; BATCH PLANT; BENDING MACHINE; CONCRETE BREAKER; CONCRETE SPREADER; CURB CUTTER MACHINE; FARM TRACTOR (ALL TYPES); FINISHING MACHINE-CONCRETE; HEPAVAC CLEAN AIR MACHINE (ALL SIMILAR TYPES: REMOVAL OF ASBESTOS ETC.); MATERIAL HOPPER-SAND-STONE-CEMENT; MIXER-CONCRETE-UNDER 21E; MULCHING GRASS SPREADER; PUMP-GYPSUM, ETC., PUMP-PLASTER-GROUT -FIREPROOFING; SHOP MECHANIC (NOT EMPLOYED ON JOB SITE); ROLLER UNDER 4 TON; SPREADING AND FINE GRADING MACHINE; STEEL CUTTING MACHINE; SYPHON PUMP-AIR-STEAM; TAR JOINT MACHINE; TURBO JET BURNER OR SIMILAR EQUIPMENT; VIBRATOR (1 TO 5); FINE GRADING MACHINE; ROOF HOIST (TUGGER HOIST); TELEVISION CAMERAS-WATER- SEWER-GAS-ETC. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $54.33 | $31.32 | $85.65 |
| POWER EQUIPMENT OPERATORS: GROUP 3-B (BUILDING CONSTRUCTION) COMPRESSOR OVER 125 CU. FEET; CONVEYOR BELT MACHINE REGARDLESS OF SIZE; LIGHTING UNIT (PORTABLE & GENERATOR); WELDING MACHINE (STEEL ERECTION AND EXCAVATION); AND COMPRESSOR PLANT; STUD MACHINE; LADDER HOIST. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $52.25 | $31.32 | $83.57 |
| POWER EQUIPMENT OPERATORS: GROUP 3-A (BUILDING CONSTRUCTION) ASPHALT PLANT; BOILER (HIGH PRESSURE); CONCRETE MIXING PLANTS; CONCRETE PUMP; FIREMEN; FORKLIFT; FORKLIFT (ELECTRIC); JOY DRILL OR SIMILAR TRACTOR DRILLING MACHINE; LOADER - 1 1/2 YARDS AND UNDER; LOCOMOTIVE (ALL SIZES); MIXER CONCRETE - 21E AND OVER; PORTABLE ASPHALT PLANT; PORTABLE BATCH PLANT; PORTABLE CRUSHER; QUARRY MASTER; STONE CRUSHER; WELL DRILLING MACHINE AND WELL POINT SYSTEM; CHERRY PICKER UNDER 10 TONS; HYDRAULIC CRANE UNDER 10 TONS; CONCERT BUFFY; ONE YARD AN UP RIDE ON DUMPER (BENFORD OR SIMILAR). PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $54.88 | $31.32 | $86.20 |
| POWER EQUIPMENT OPERATORS: GROUP 2-A (BUILDING CONSTRUCTION) COMPACTOR SELF-PROPELLED; GRADER; BULLDOZE D7 AND SIMILAR TRACTORS WITH A DRAW BAR HORSEPOWER OF 100 OR OVER; BULLDOZER D6 AND UNDER; WELDER; SCRAPER 20 YDS STRUCK AND UNDER; MACHINE PULLING SHEEP'S FOOT ROLLER; VIBRATORY ROLLERS. PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $56.97 | $31.32 | $88.29 |
| POWER EQUIPMENT OPERATORS: GROUP 1-B (BUILDING CONSTRUCTION) COMPRESSOR (STEEL ERECTION); PULSE METER AND PUSH BUTTON BUZZ BOX; ELEVATOR; MECHANIC (OUTSIDE) ALL TYPES; WELDER; SCRAPERS 20 YDS STRUCK AND UNDER; MACHINE PULLING SHEEP'S FOOT ROLLER; VIBRATORY ROLLERS; ROLLER 4 TONS AND OVER. NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $54.41 | $31.32 | $85.73 |
| POWER EQUIPMENT OPERATORS: GROUP 1-A (BUILDING CONSTRUCTION) CARRIER- TRAILER HORSE; CONCRET-PORTABLE HOIST; CRANE & HOIST ENGINEER-STEEL (CONCRETE, MATERIAL, SUPER STRUCTURE SUB- STRUCTURE); DERRICK (STONE-STEEL); ELEVATOR & CAGE; HOIST- SINGLE/DOUBLE OR TRIPLE DRUM; HOIST-PORTABLE MOBILE UNIT; HOIST ENGINEER-CONCERT (CRANE-DERRICK-MINE HOIST); HOIST ENGINEER- MATERIAL; OVERHEAD CRANE; POWER HOUSE PLANT; TELEPHIES (CABLEWAY); WHIRLY; MAINTENANCE ENGINEER; LULL HILIFT OR SIMILAR; HYDRAULIC CRANE 25 TON AND OVER; CHERRY PICKER 25 TONS AND OVER; BACKHOE OLIVER 88; FORDSON; DYNAHOE; DUAL PURPOSE AND SIMILAR MACHINES; BARBER GREEN LOADER-EUCLID LOADER OR SIMILAR TYPE; CONWAY OR SIMILAR MUCKING MACKING MACHINES; DRAGLINE; GRADALL; SHOVEL; BACKHOE ETC. (CRAWLER OR TRUCK); FRONT END LOADERS; HYDRAULIC BOOM; JERSEY SPREADER; LIFT SLAB CONSOLE; LETOURNEQU OR TOUNAPULL (SCRAPERS OVER 20 YDS STRUCK); MUCKING MACHINES; PAVEMENT BREAKER (AIR RAM); PAVER (CONCRETE); ROAD BORING MACHINE; ROAD MIX MACHINES; ROSS CARRIER AND SIMILAR MACHINES; POST HOLE DIGGER; SHOVEL (TUNNELS); SIDE BOOM; SPREADER (ASPHALT); SCOOPMOBILE-TRACTOR-SHOVEL OVER 1 1/2 YDS. TRENCHING MACHINES VERMEER CONCRETE SAW TRENCHER AND SIMILAR; TRACTOR TYPE DEMOLITION EQUIPMENT; WINCH TRUCK (A FRAME); HYDRAULIC CRANE OVER 10 TON UP TO 25 TON); CHERRY PICKER OVER 10 TON UP TO 25 TON) NOTES: HAZMAT: 20% ABOVE REGULAR RATE PUMPING OPERATION PREMIUM .50 CRANE OPERATORS (100-149 FT) 2.00 CRANE OPERATORS (149 FT +) 3.00 LOADER OPERATORS (OVER 5 CU Y) .50 SHOVEL OPERATORS (OVER 4 CU YD)1.00 FOOTNOTE: A. NEW YEARS DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY THANKSGIVING DAY, CHRISTMAS DAY, PLUS LINCOLN'S BIRTHDAY, WASHINGTON'S BIRTHDAY, GOOD FRIDAY, COLUMBUS DAY, NOVEMBER ELECTION DAY, VETERAN'S DAY | $59.04 | $31.32 | $90.36 |
ENGI0137-006 Effective 03/04/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: GROUP 5-A-5 JERSEY-SPREADER, PAVEMENT BREAKER (AIR RAM); POST HOLE DIGGER (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $59.19 | $35.25 | $94.44 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-4 HOIST ENGINEER- STEEL -SUB STRUCTURE (HEAVY & HIGHWAY) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $70.41 | $35.25 | $105.66 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-3 ENGINEER-- PILE DRIVER (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $75.13 | $35.25 | $110.38 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-2 ENGINEER - ALL TOWER CRANES, ALL CLIMBING CRANES AND ALL CRANES OF 100 TON CAPACITY OR GREATER (3900 MANITOWAC OR SIMILAR) IRRESPECTIVE OF MANUFACTURER AND REGARDLESS OF HOW THE SAME IS RIGGED (EXCEPT FOR PILE RIGS). (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $77.82 | $35.25 | $113.07 |
| POWER EQUIPMENT OPERATORS: GROUP 5-A-1 MASTER MECHANIC (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $64.02 | $35.25 | $99.27 |
| POWER EQUIPMENT OPERATORS: GROUP 5 OILER (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $64.02 | $35.25 | $99.27 |
| POWER EQUIPMENT OPERATORS: GROUP 4-B OILER; COMPRESSOR - COMPRESSOR PLANT; PAINT COMPRESSOR-STEEL ERECTION; CONVEYOR BELT MACHINE; LIGHTING UNIT (PORTABLE & GENERATOR); OILER; PUMPS - PUMP STATION-WATER-SEWER- GYPSUM- PLASTER, ETC.; ROLLER-MOTORIZED (WALK-BEHIND); WELDING MACHINE (STEEL ERECTION EXCAVATION); WELL POINT SYSTEM; BENDING MACHINE; DUST COLLECTOR; MIXER - CONCRETE UNDER 21-E; HEATER ALL TYPES; STEAM JENNY; SYPHON PUMP-AIR-STEAM; TAR JOINT MACHINE; VIBRATOR (1 TO 5); COMPRESSOR TRUCK MOUNTED (2-6) (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $44.19 | $35.25 | $79.44 |
| POWER EQUIPMENT OPERATORS: GROUP 4-A SERVICE MEN (FUEL OR GREASE TRUCK). (HEAVY & HIGHWAY) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $51.57 | $35.25 | $86.82 |
| POWER EQUIPMENT OPERATORS: GROUP 3 A: AIR TRACTOR DRILL; ASPHALT PLANT; BATCH PLANT; BOILER (HIGH PRESSURE; CONCRETE BREAKER; CONCRETE PUMP CONCRETE SPREADER; CURB CUTTER MACHINE; FARM TRACTOR (ALL TYPES); FINISHING MACHINE (CONCRETE); FINE GRADING MACHINE; FIREMAN; FORKLIFT; FORKLIFT (ELECTRIC); JOY DRILL OR SIMILAR TRACTOR DRILLING MACHINE; LOADER - 1 1/2 YARDS AND UNDER; LOCOMOTIVE (ALL SIZES), MAINTENANCE ENGINEER; MACHINE PULLING SHEEPS FOOT ROLLER; MATERIAL HOPPER; MIXER CONCRETE - 21-E AND OVER; MULCHING GRASS SPREADER; PORTABLE ASPHALT PLANT, PORTABLE BATCH PLANT, PORTABLE CRUSHER; POWERHOUSE PLANT; QUARRY MASTER; ROLLER UNDER 4 TON; SPREADING AND FINE GRADING MACHINE; STEEL CUTTING MACHINE; STONE CRUSHER; SWEEPER; TURBOJET BURNER OR SIMILAR; WELL DRILLING MACHINE ; WINCH TRUCK ""A"" FRAME. JOHN HENRY DRILL OR SIMILAR. (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $56.81 | $35.25 | $92.06 |
| POWER EQUIPMENT OPERATORS: GROUP 2-B MECHANIC (OUTSIDE) ALL TYPES (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $59.67 | $35.25 | $94.92 |
| POWER EQUIPMENT OPERATORS: GROUP 1-B ROAD PAVER, ASPHALT (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $63.70 | $35.25 | $98.95 |
| POWER EQUIPMENT OPERATORS: GROUP 1-A AUGER; AUTO GRADER; DYNAHOE AND DUAL PURPOSE AND SIMILAR MACHINES; BOAT CAPTAIN; BORING MACHINE (ALL TYPES); BULL DOZER-ALL SIZES; CENTRAL MIX PLANT OPERATOR; CHIPPER-ALL TYPES; CLOSE CIRCUIT T.V.; COMPACTOR WITH BLADE; CONCRETE PORTABLE HOIST; C.M.I. OR SIMILAR; CONWAY OR SIMILAR MUCKING MACHINES; GRADALL, SHOVEL BACKHOE, ETC. GRADER; DERRICK, (STONE- STEEL; ELEVATOR & CAGE, MATERIALS OR PASSENGERS; FRONT END LOADERS OVER 1 1/2 YDS.; HOIST SINGLE, DOUBLE, TRIPLE DRUM, HOIST PORTABLE MOBILE UNIT; HOIST ENGINEER-CONCRETE (CRANE-DERRICK-MINE HOIST); HOIST ENGINEER-MATERIAL, HYDRAULIC BOOM; LETOURNEAU OR TOURNAPULL (SCRAPERS OVER 20 YDS. STRUCK); LOG SKIDDER; MOVABLE CONCRETE BARRIER TRANSFER & TRANSPORT VEHICLE; MUCKING MACHINES; OVERHEAD CRANE; PAVER (CONCCRETE); PULSEMETER; PUSH BUTTON (BUZZ BOX) ELEVATOR; ROAD MIX MACHINES; ROBOT HAMMER (BROCK OR SIMILAR), ROSS CARRIER AND SIMILAR MACHINES; SHOVELS (TUNNELS); SIDE BOOM; SLIP FORM MACHINE; SPREADER (ASPHALT); SCOOPMOBILE-TRACTOR-SHOVEL OVER 1 1/2 YARDS; TRENCHING MACHINES; TELEPHIES- VERMEER CONCRETE SAW TRENCHER AND/OR SIMILAR; TRACTOR-TYPE DEMOLITION EQUIPMENT, WHIRLY (HEAVY & HIGHWAY) NOTES: LOADER OPERATOR (OVER 5 CU YDS) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $60.42 | $35.25 | $95.67 |
| POWER EQUIPMENT OPERATORS: GROUP 1 BOOM TRUCK; CHERRY PICKER; CLAMSHELL; CRANE (CRAWLER, TRUCK); DRAGLINE; ROUGH TERRAIN CRANE (HEAVY & HIGHWAY) .50 SHOVAL OPERATORS (OVER 4 CU YD) 1.00 HAZMAT PREMIUM OVER REGULAR RATE 20% CRANES: 100 FT- 149 FT: RECEIVE $2.00 MORE THAN GROUP 1 RATE 149 FT AND OVER RECEIVE $3.00 MORE THAN GROUP 1 RATE FOOTNOTE: A. PAID HOLIDAYS: NEW YEAR'S DAY; LINCOLN'S BIRTHDAY; GOOD FRIDAY; MEMORIAL DAY; INDEPENDENCE DAY; LABOR DAY; VETERANS DAY; COLUMBUS DAY; NOVEMBER ELECTION DAY; THANKSGIVING DAY; AND CHRISTMAS DAY | $68.63 | $35.25 | $103.88 |
IRON0417-001 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER A) PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING (UNPAID), CHRISTMAS DAY | $42.63 | $53.70 | $96.33 |
LABO0235-001 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER (BUILDING) | $44.05 | $32.40 | $76.45 |
LABO0235-004 Effective 05/01/2023 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: HIGHWAY: GROUP 3 ASPHALT RAKER, ASPHALT SCREEMAN, DRILLERS (ALL), LASER BEAM OPERATOR, FORM SETTER/ALIGNERS, BLASTERS, LEAD MAN, TUNNEL & CAISSON FOOTNOTE: A. PAID HOLIDAYS: NEW YEARS DAY, PRESIDENTS DAY, GOOD FRIDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERAN'S DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $43.90 | $27.80 | $71.70 |
PAIN0009-003 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PAINTER (SPRAY, SCAFFOLD, SANDBLASTING) | $47.75 | $44.11 | $91.86 |
| PAINTER (PAINTERS, PAPERHANGER, DRYWALL FINISHERS & LEAD ABATEMENT WORKER) | $44.75 | $44.11 | $88.86 |
| PAINTER (GLAZIERS) | $49.20 | $57.20 | $106.40 |
PLUM0021-001 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER AND STEAMFITTER (ZONE 1) | $65.07 | $45.35 | $110.42 |
ROOF0008-002 Effective 05/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ROOFER | $50.25 | $32.62 | $82.87 |
SFNY0669-002 Effective 01/01/2026 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SPRINKLER FITTER | $57.20 | $32.66 | $89.86 |
SHEE0038-001 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL WORKER | $55.29 | $47.43 | $102.72 |
TEAM0456-001 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVERS: GROUP 11 OFF ROAD EQUIPMENT (UNDER 40 TONS) DJB HAZARDOUS/TOXIC WASTE - AN ADDITIONAL 20% OF THE BASIC HOURLY WAGE RATE SET FORTH IN THIS WAGE DETERMINATION. A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY, PROVIDED EMPLOYEE WORKS TWO OR MORE DAYS IN THE CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. PAID VACATION: 4 WEEKS PAID VACATION AFTER 20 YEARS OF SERVICE AND 30 DAYS OF EMPLOYMENT IN CURRENT CONTRACT YEAR; 3 WEEKS AFTER 10 YEARS OF SENIORITY SERVICE; 3 WEEKS AFTER 10 YEARS AND 60 DAYS OF EMPLOYMENT IN CONTRACT YEAR, 3 WEEKS AND 1 DAY AFTER 16 YEARS OF SENIORITY SERVICE, 3 WEEKS AND 2 DAYS AFTER 17 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 3 DAYS AFTER 18 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 4 DAYS AFTER 19 YEARS OF SENIORITY SERVICE; THE THIRD WEEK AND EVERY ADDITIONAL DAY SHALL BE GRANTED TO EMPLOYEE IN THE CALENDAR YEAR IN WHICH HE COMPLETES HIS TENTH OR OTHER YEARS OF SENIORITY SERVICE; 2 WEEKS AFTER 130 DAYS OF EMPLOYMENT IN THE CALENDAR YEAR; 2 WEEKS AFTER 5 YEARS AND 90 DAYS SENIORITY SERVICE IN CALANDER YEAR; 1 WEEK AND 1 ADDITIONAL DAY FOR EACH ADDITIONAL 18 DAYS OF EMPLOYMENT NOT EXCEEDING 10 DAYS IN ANY ONE CALANDER YEAR AFTER 90 DAYS OF EMPLOYMENT. CASUAL EMPLOYEES 1 DAY FOR EVERY 18 DAYS OF EMPLOYMENT. AN EMPLOYEE WHO DOES NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND: EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | $50.26 | $38.93 | $89.19 |
| TRUCK DRIVERS: GROUP 10 OFF ROAD EQUIPMENT (OVER 40 TONS) EUCLID, DJB HAZARDOUS/TOXIC WASTE - AN ADDITIONAL 20% OF THE BASIC HOURLY WAGE RATE SET FORTH IN THIS WAGE DETERMINATION. A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY, PROVIDED EMPLOYEE WORKS TWO OR MORE DAYS IN THE CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. PAID VACATION: 4 WEEKS PAID VACATION AFTER 20 YEARS OF SERVICE AND 30 DAYS OF EMPLOYMENT IN CURRENT CONTRACT YEAR; 3 WEEKS AFTER 10 YEARS OF SENIORITY SERVICE; 3 WEEKS AFTER 10 YEARS AND 60 DAYS OF EMPLOYMENT IN CONTRACT YEAR, 3 WEEKS AND 1 DAY AFTER 16 YEARS OF SENIORITY SERVICE, 3 WEEKS AND 2 DAYS AFTER 17 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 3 DAYS AFTER 18 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 4 DAYS AFTER 19 YEARS OF SENIORITY SERVICE; THE THIRD WEEK AND EVERY ADDITIONAL DAY SHALL BE GRANTED TO EMPLOYEE IN THE CALENDAR YEAR IN WHICH HE COMPLETES HIS TENTH OR OTHER YEARS OF SENIORITY SERVICE; 2 WEEKS AFTER 130 DAYS OF EMPLOYMENT IN THE CALENDAR YEAR; 2 WEEKS AFTER 5 YEARS AND 90 DAYS SENIORITY SERVICE IN CALANDER YEAR; 1 WEEK AND 1 ADDITIONAL DAY FOR EACH ADDITIONAL 18 DAYS OF EMPLOYMENT NOT EXCEEDING 10 DAYS IN ANY ONE CALANDER YEAR AFTER 90 DAYS OF EMPLOYMENT. CASUAL EMPLOYEES 1 DAY FOR EVERY 18 DAYS OF EMPLOYMENT. AN EMPLOYEE WHO DOES NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND: EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | $50.51 | $38.93 | $89.44 |
| TRUCK DRIVERS: GROUP 9 OFF ROAD EQUIPMENT (UNDER 40 TONS): EUCLID HAZARDOUS/TOXIC WASTE - AN ADDITIONAL 20% OF THE BASIC HOURLY WAGE RATE SET FORTH IN THIS WAGE DETERMINATION. A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY, PROVIDED EMPLOYEE WORKS TWO OR MORE DAYS IN THE CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. PAID VACATION: 4 WEEKS PAID VACATION AFTER 20 YEARS OF SERVICE AND 30 DAYS OF EMPLOYMENT IN CURRENT CONTRACT YEAR; 3 WEEKS AFTER 10 YEARS OF SENIORITY SERVICE; 3 WEEKS AFTER 10 YEARS AND 60 DAYS OF EMPLOYMENT IN CONTRACT YEAR, 3 WEEKS AND 1 DAY AFTER 16 YEARS OF SENIORITY SERVICE, 3 WEEKS AND 2 DAYS AFTER 17 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 3 DAYS AFTER 18 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 4 DAYS AFTER 19 YEARS OF SENIORITY SERVICE; THE THIRD WEEK AND EVERY ADDITIONAL DAY SHALL BE GRANTED TO EMPLOYEE IN THE CALENDAR YEAR IN WHICH HE COMPLETES HIS TENTH OR OTHER YEARS OF SENIORITY SERVICE; 2 WEEKS AFTER 130 DAYS OF EMPLOYMENT IN THE CALENDAR YEAR; 2 WEEKS AFTER 5 YEARS AND 90 DAYS SENIORITY SERVICE IN CALANDER YEAR; 1 WEEK AND 1 ADDITIONAL DAY FOR EACH ADDITIONAL 18 DAYS OF EMPLOYMENT NOT EXCEEDING 10 DAYS IN ANY ONE CALANDER YEAR AFTER 90 DAYS OF EMPLOYMENT. CASUAL EMPLOYEES 1 DAY FOR EVERY 18 DAYS OF EMPLOYMENT. AN EMPLOYEE WHO DOES NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND: EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | $49.88 | $38.93 | $88.81 |
| TRUCK DRIVERS: GROUP 4 TRACTOR TRAILERS (ALL TYPES) HAZARDOUS/TOXIC WASTE - AN ADDITIONAL 20% OF THE BASIC HOURLY WAGE RATE SET FORTH IN THIS WAGE DETERMINATION. A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY, PROVIDED EMPLOYEE WORKS TWO OR MORE DAYS IN THE CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. PAID VACATION: 4 WEEKS PAID VACATION AFTER 20 YEARS OF SERVICE AND 30 DAYS OF EMPLOYMENT IN CURRENT CONTRACT YEAR; 3 WEEKS AFTER 10 YEARS OF SENIORITY SERVICE; 3 WEEKS AFTER 10 YEARS AND 60 DAYS OF EMPLOYMENT IN CONTRACT YEAR, 3 WEEKS AND 1 DAY AFTER 16 YEARS OF SENIORITY SERVICE, 3 WEEKS AND 2 DAYS AFTER 17 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 3 DAYS AFTER 18 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 4 DAYS AFTER 19 YEARS OF SENIORITY SERVICE; THE THIRD WEEK AND EVERY ADDITIONAL DAY SHALL BE GRANTED TO EMPLOYEE IN THE CALENDAR YEAR IN WHICH HE COMPLETES HIS TENTH OR OTHER YEARS OF SENIORITY SERVICE; 2 WEEKS AFTER 130 DAYS OF EMPLOYMENT IN THE CALENDAR YEAR; 2 WEEKS AFTER 5 YEARS AND 90 DAYS SENIORITY SERVICE IN CALANDER YEAR; 1 WEEK AND 1 ADDITIONAL DAY FOR EACH ADDITIONAL 18 DAYS OF EMPLOYMENT NOT EXCEEDING 10 DAYS IN ANY ONE CALANDER YEAR AFTER 90 DAYS OF EMPLOYMENT. CASUAL EMPLOYEES 1 DAY FOR EVERY 18 DAYS OF EMPLOYMENT. AN EMPLOYEE WHO DOES NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND: EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | $49.13 | $38.93 | $88.06 |
|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| $48.51 | $38.93 | $87.44 |
| TRUCK DRIVERS: GROUP 1 LOWBOY (CARRYING EQUIPMENT) HAZARDOUS/TOXIC WASTE - AN ADDITIONAL 20% OF THE BASIC HOURLY WAGE RATE SET FORTH IN THIS WAGE DETERMINATION. A. PAID HOLIDAYS: NEW YEAR'S DAY, LINCOLN'S BIRTHDAY, PRESIDENT'S DAY, DECORATION DAY, INDEPENDENCE DAY, LABOR DAY, NOVEMBER ELECTION DAY, THANKSGIVING DAY, DAY AFTER THANKSGIVING AND CHRISTMAS DAY, PROVIDED EMPLOYEE WORKS TWO OR MORE DAYS IN THE CALENDAR WEEK IN WHICH THE HOLIDAY FALLS. PAID VACATION: 4 WEEKS PAID VACATION AFTER 20 YEARS OF SERVICE AND 30 DAYS OF EMPLOYMENT IN CURRENT CONTRACT YEAR; 3 WEEKS AFTER 10 YEARS OF SENIORITY SERVICE; 3 WEEKS AFTER 10 YEARS AND 60 DAYS OF EMPLOYMENT IN CONTRACT YEAR, 3 WEEKS AND 1 DAY AFTER 16 YEARS OF SENIORITY SERVICE, 3 WEEKS AND 2 DAYS AFTER 17 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 3 DAYS AFTER 18 YEARS OF SENIORITY SERVICE; 3 WEEKS AND 4 DAYS AFTER 19 YEARS OF SENIORITY SERVICE; THE THIRD WEEK AND EVERY ADDITIONAL DAY SHALL BE GRANTED TO EMPLOYEE IN THE CALENDAR YEAR IN WHICH HE COMPLETES HIS TENTH OR OTHER YEARS OF SENIORITY SERVICE; 2 WEEKS AFTER 130 DAYS OF EMPLOYMENT IN THE CALENDAR YEAR; 2 WEEKS AFTER 5 YEARS AND 90 DAYS SENIORITY SERVICE IN CALANDER YEAR; 1 WEEK AND 1 ADDITIONAL DAY FOR EACH ADDITIONAL 18 DAYS OF EMPLOYMENT NOT EXCEEDING 10 DAYS IN ANY ONE CALANDER YEAR AFTER 90 DAYS OF EMPLOYMENT. CASUAL EMPLOYEES 1 DAY FOR EVERY 18 DAYS OF EMPLOYMENT. AN EMPLOYEE WHO DOES NOT QUALIFY FOR VACATION SHALL BE PAID PRO RATA ON A DAILY BASIS. HOLIDAY SHALL BE COUNTED AS DAYS WORKED FOR VACATION BENEFITS. LEGAL SERVICES FUND: EMPLOYER SHALL CONTRIBUTE $.20 TO THE FUND ON THE SAME BASIS FOR ALL HOURS PAID TO EMPLOYEES IN THE FORM OF HOLIDAY PAY OR VACATION PAY. IN ADDITION TO THE BENEFITS PAID FOR HEALTH-WELFARE AND PENSION FOR UP TO 40 HOURS WORKED AN ADDITIONAL $.25 IS PAID FOR EACH HOUR WORKED. THE EMPLOYER SHALL GRANT 3 CALENDAR DAYS OFF WITHOUT LOSS OF PAY TO AN EMPLOYEE WHO HAS DEATH IN HIS/HER IMMEDIATE FAMILY, INCLUSIVE OF THE DAY OF THE FUNERAL | $51.26 | $38.93 | $90.19 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 1 | 01/30/2026 |
| 2 | 05/18/2026 |
Counties Covered
This wage determination applies to 1 county in New York.
Get notified when NY20260025 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.