CARP0096-006 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MILLWRIGHT | $59.35 | $22.38 | $81.73 |
CARP0503-019 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (EXCLUDING FORM WORK) | $53.94 | $16.81 | $70.75 |
ELEC0048-028 Effective 01/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (SHERMAN COUNTY) | $63.50 | $29.73 | $93.23 |
ELEC0112-018 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (BAKER, GILLIAM, WALLOWA AND WHEELER COUNTIES) | $60.00 | $27.78 | $87.78 |
ELEC0280-024 Effective 01/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (CROOK COUNTY) | $56.46 | $23.05 | $79.51 |
ELEC0659-022 Effective 01/01/2026 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (HARNEY AND LAKE COUNTIES) | $47.04 | $21.84 | $68.88 |
ENGI0701-038 Effective 01/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATOR GROUP 6 OILER; GRADE CHECKER; CRANE OILER; FORKLIFT; ROLLER (NON-ASPHALT) | $45.81 | $16.90 | $62.71 |
| POWER EQUIPMENT OPERATOR GROUP 5 TRACKHOE-HYDRAULIC: TRACK TYPE UP TO AND INCLUDING 20,000 LBS, WHEEL TYPE (FORD, JOHN DEER, CASE TYPE); BOOM TRUCK OPERATOR; DRILLING: CHURM DRILL AND EARTH BORING MACHINE OPERATOR; DIRECTIONAL DRILL OPERATOR LESS THAN 20,000 LBS PULLBACK; FORKLIFT OVER 5 TON, BULLDOZER 20,000 LBS OR 100 HORSES OR LESS; ROLLER; COMPACTOR WITHOUT BLADE; HOIST OPERATOR SINGLE DRUM | $49.03 | $16.90 | $65.93 |
| POWER EQUIPMENT OPERATOR GROUP 3 HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR, 50 TONS THROUGH 89 TONS (WITHOUT LUFFING OR TOWER ATTACHMENT); LATTICE BOOM CRANES: LATTICE BOOM CRANE-50 THROUGH 89 TONS (AND LESS THAN 150 FEET BOOM); RUBBER TIRED SCRAPER: WITH TANDOM SCRAPERS; SELF LOADING, PADDLE WHEEL, AUGER TYPE, FINISH AND/OR 2 OR MORE UNITS; BULLDOZER OVER 70,000 LBS UP TO AND INCLUDING 120,000 LBS; | $53.60 | $16.90 | $70.50 |
| POWER EQUIPMENT OPERATOR GROUP 2 CRANE: CABLEWAY OPERATOR, 25 TONS AND OVER; HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR 90 TONS THROUGH 199 TONS (WITHOUT LUFFING OR TOWER ATTACHMENT); TOWER/WHIRLEY OPERATOR: TOWER CRANE OPERATOR; WHIRLEY OPERATOR, UNDER 90 TONS; LATTICE BOOM CRANE: 90 THROUGH 199 TONS AND/OR 150 TO 200 FEET BOOM; HYDRAULIC CRANE: HYDRAULIC CRANE OPERATOR, 50 TONS THROUGH 89 TONS (WITH LUFFING OR TOWER ATTACHMENT); RUBBER TIRED SCRAPER WITH TANDOM SCRAPERS; BLADE: AUTO GRADER; BLADE OPERATOR-ROBOTIC; BULLDOZER OVER 120,000 LBS AND ABOVE; | $54.75 | $16.90 | $71.65 |
| POWER EQUIPMENT OPERATOR GROUP 1B LATTICE BOOM CRANE: OPERATOR, 300 TONS THROUGH 399 TONS WITH OVER 200 FEET BOOM; OPERATOR 400 TONS AND OVER | $60.98 | $16.90 | $77.88 |
| POWER EQUIPMENT OPERATOR GROUP 1A HYDRAULIC CRANE: HYDRAULIC OPERATOR, 200 TONS AND OVER (WITH LUFFING OR TOWER ATTACHMENT); LATTICE BOOM CRANE: OPERATOR, 200 TONS THROUGH 299 TONS, WITH OVER 200 FEET BOOM; | $58.82 | $16.90 | $75.72 |
IRON0029-013 Effective 07/07/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER (REINFORCING AND STRUCTURAL) | $48.31 | $34.52 | $82.83 |
LABO0737-005 Effective 06/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: (MASON TENDER-CEMENT/CONCRETE) | $43.79 | $17.05 | $60.84 |
LABO0737-031 Effective 06/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: GROUP 2 GRADE CHECKER | $40.41 | $17.30 | $57.71 |
| LABORERS: GROUP 1 ASPHALT SPREADER | $39.11 | $17.30 | $56.41 |
PAIN0010-006 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PAINTERS: (BRUSH, ROLLER AND SPRAY) | $39.94 | $16.68 | $56.62 |
PLUM0290-017 Effective 04/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBERS AND PIPEFITTERS (CROOK, GILLIAM, HARNEY (THOSE PORTIONS WHICH LIES NORTH AND WEST OF A NORTH-SOUTH LINE DRAWN FROM THE TOWN OF JOHN DAY TO A POINT FIVE MILES EAST OF THE TOWN OF BURNS AND THREE MILES SOUTH OF BURNS THENCE ON AN AIRLINE THROUGH THE TOWN OF WAGONTIRE WEST TO THE COUNTY LINES), LAKE, SHERMAN AND WHEELER COUNTIES) | $60.77 | $34.72 | $95.49 |
PLUM0296-010 Effective 06/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBERS AND PIPEFITTERS (BAKER AND HARNEY (REMAINDER OF COUNTY) COUNTIES) | $39.90 | $18.67 | $58.57 |
PLUM0598-021 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBERS AND PIPEFITTERS (WALLOWA COUNTY) | $65.20 | $34.91 | $100.11 |
SUOR2009-078 Effective 11/23/2009 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: WATER TRUCK | $26.12 | $6.53 | $32.65 |
| TRUCK DRIVER: OFF THE ROAD TRUCK | $31.81 | $6.33 | $38.14 |
| TRUCK DRIVER: DUMP TRUCK | $23.79 | $5.95 | $29.74 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $27.59 | $2.96 | $30.55 |
| OPERATOR: LOADER | $32.31 | $6.43 | $38.74 |
| OPERATOR: EXCAVATOR | $30.12 | $6.23 | $36.35 |
| OPERATOR: BROOM/SWEEPER | $32.31 | $6.43 | $38.74 |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER | $22.77 | $7.90 | $30.67 |
| OPERATOR: BACKHOE | $29.80 | $7.13 | $36.93 |
| LINE CONSTRUCTION: GROUNDMAN | $31.36 | $7.27 | $38.63 |
| LABORER: PIPELAYER | $20.52 | $4.51 | $25.03 |
| LABORER: FLAGGER | $19.31 | $5.31 | $24.62 |
| LABORER: FENCE ERECTION | $23.88 | $7.45 | $31.33 |
| LABORER: COMMON OR GENERAL | $22.29 | $6.04 | $28.33 |
| CEMENT MASON/CONCRETE FINISHER | $21.13 | $8.90 | $30.03 |
| CARPENTER (FORM WORK ONLY) | $23.50 | $9.27 | $32.77 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 1 | 01/23/2026 |
| 2 | 05/18/2026 |
Counties Covered
This wage determination applies to 8 counties in Oregon.
Get notified when OR20260080 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.