Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0034-007 Effective 06/09/2025
Trade Rate Fringe Total
ASBESTOS WORKER/HEAT & FROST INSULATOR (DUCT, PIPE & MECHANICAL SYSTEM INSULATION) $55.34 $34.03 $89.37
BRSD0002-003 Effective 05/01/2022
Trade Rate Fringe Total
BRICKLAYER $38.16 $5.59 $43.75
ENGI0049-009 Effective 09/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR ((3) HYDRO CRANE; CRANE (ALL OTHER TYPES)) LONG BOOM PAY: 151' TO 200' - PER HOUR. MEASUREMENT SHALL BE FROM BUTT PINS OF THE BOOM TO THE TOP OF THE SHEAVE OR JIB SHEAVE. TOWER CRANE PREMIUM: FROM THE TOP OF THE TOWER CRANE FOUNDATION TO THE TOP OF THE TOWER CRANE APEX. IN THE CASE OF LUFFING CRANES, TO THE TOP OF GANTRY, PLUS BOOM LENGTH PER CLASSIFICATION: 250' TO 299' - $1.00 300' TO 349 - $1.50 350' TO 399' - $2.00 400' TO 449' - $2.50 450' AND OVER - $3.00 $34.08 $18.71 $52.79
POWER EQUIPMENT OPERATOR ((1) TOWER CRANE): LONG BOOM PAY: 151' TO 200' - $0.50 PER HOUR ADDITIONAL; 201' AND OVER - $0.60 PER HOUR. MEASUREMENT SHALL BE FROM BUTT PINS OF THE BOOM TO THE TOP OF THE SHEAVE OR JIB SHEAVE. TOWER CRANE PREMIUM: FROM THE TOP OF THE TOWER CRANE FOUNDATION TO THE TOP OF THE TOWER CRANE APEX. IN THE CASE OF LUFFING CRANES, TO THE TOP OF GANTRY, PLUS BOOM LENGTH PER CLASSIFICATION: 250' TO 299' - $1.00 300' TO 349 - $1.50 350' TO 399' - $2.00 400' TO 449' - $2.50 450' AND OVER - $3.00 $34.38 $18.71 $53.09
IRON0021-018 Effective 05/01/2024
Trade Rate Fringe Total
IRONWORKER, STRUCTURAL $30.80 $15.48 $46.28
SUSD2012-017 Effective 08/21/2014
Trade Rate Fringe Total
SHEET METAL WORKER (HVAC DUCT INSTALLATION ONLY) $20.41 $9.64 $30.05
ROOFER $14.35 $2.14 $16.49
PLUMBER $14.02 $1.90 $15.92
PAINTER: BRUSH, ROLLER, AND SPRAY $18.80 $4.99 $23.79
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $20.57 $0.00 $20.57
OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $19.34 $0.00 $19.34
LABORER: MASON TENDER - BRICK $14.19 $0.00 $14.19
LABORER: COMMON OR GENERAL $10.74 $0.00 $10.74
ELECTRICIAN $22.60 $7.69 $30.29
CEMENT MASON/CONCRETE FINISHER $20.67 $11.85 $32.52
CARPENTER $15.96 $4.15 $20.11

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in South Dakota.

Get notified when SD20260020 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.