UT20260036
ResidentialDavis-Bacon Act general wage determination for residential construction in Utah.
Track UT20260036
Get an email when this wage determination gets a new modification.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Wage Rates
Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.
ENGI0003-052 Effective 07/01/2013 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| OPERATOR: POWER EQUIPMENT: (7) ROLLER (DIRT AND GRADE COMPACTION) | $21.50 | $15.65 | $37.15 |
| OPERATOR: POWER EQUIPMENT: (5) ASPHALT ROLLER, FRONT END LOADER (UNDER 2 CU. YDS.) | $23.37 | $15.65 | $39.02 |
| OPERATOR: POWER EQUIPMENT: (4) ASPHALT PAVER, BACKHOE LOADER COMBO, BULLDOZER, FRONT END LOADER (2 TO 5 CU. YDS.), OIL DISTRIBUTOR | $24.37 | $15.65 | $40.02 |
| OPERATOR: POWER EQUIPMENT: (3) BACKHOE/EXCAVATOR, FRONT END LOADER (OVER 5 CU. YDS. ) | $25.37 | $15.65 | $41.02 |
| OPERATOR: POWER EQUIPMENT: (2A) BLADE/GRADER | $25.89 | $15.65 | $41.54 |
| OPERATOR: POWER EQUIPMENT: (1) MECHANIC | $27.55 | $15.65 | $43.20 |
| OPERATOR: POWER EQUIPMENT (6) SCREED | $22.41 | $15.65 | $38.06 |
LABO0295-020 Effective 07/01/2012 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER (CHAIN/CONCRETE SAW, JACKHAMMER AND VIBRATOR) | $18.63 | $6.35 | $24.98 |
PLAS0568-001 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CEMENT MASON/CONCRETE FINISHER | $36.66 | $11.25 | $47.91 |
PLUM0140-016 Effective 08/01/2019 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER (EXCLUDING HVAC PIPE INSTALLATION) | $30.60 | $10.85 | $41.45 |
SFUT0669-002 Effective 01/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SPRINKLER FITTER | $38.17 | $25.54 | $63.71 |
SUUT2008-051 Effective 08/28/2008 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| SHEET METAL WORKER, INCLUDES HVAC DUCT, PIPE AND UNIT INSTALLATION | $15.31 | $0.00 | $15.31 |
| ROOFER | $17.14 | $0.00 | $17.14 |
| PAINTER: BRUSH, ROLLER AND SPRAY, EXCLUDES DRYWALL FINISHING/TAPING | $11.23 | $0.00 | $11.23 |
| OPERATOR: TRACKHOE | $14.89 | $0.00 | $14.89 |
| LABORER: MASON TENDER (BRICK AND HOD) | $12.00 | $0.00 | $12.00 |
| LABORER: MASON TENDER - CEMENT/CONCRETE | $12.95 | $0.00 | $12.95 |
| LABORER: LANDSCAPE | $10.00 | $0.19 | $10.19 |
| LABORER: COMMON OR GENERAL | $11.54 | $3.63 | $15.17 |
| LABORER: ASPHALT SHOVELER | $12.95 | $0.00 | $12.95 |
| LABORER: ASPHALT RAKER | $13.00 | $0.00 | $13.00 |
| ELECTRICIAN | $16.06 | $1.97 | $18.03 |
| DRYWALL HANGER | $18.82 | $0.00 | $18.82 |
| DRYWALL FINISHER/TAPER | $17.90 | $1.96 | $19.86 |
| CARPENTER, INCLUDES METAL STUD INSTALLATION, AND SIDING INSTALLATION (EXCLUDES DRYWALL HANGING) | $15.26 | $0.00 | $15.26 |
| BRICKLAYER | $17.92 | $0.00 | $17.92 |
TEAM0222-018 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: WATER, FUEL & OIL TANK (LESS THAN 1,200 GAL.) | $29.37 | $14.65 | $44.02 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (6,000 GAL. TO LESS THAN 10,000 GAL) | $28.60 | $14.65 | $43.25 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (4,000 GAL. TO LESS THAN 6,000 GAL) | $28.33 | $14.65 | $42.98 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (25,000 GAL. AND OVER) | $31.20 | $14.65 | $45.85 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (20,000 GAL. TO LESS THAN 25,000 GAL) | $31.04 | $14.65 | $45.69 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (2,500 GAL. TO LESS THAN 4,000 GAL) | $29.53 | $14.65 | $44.18 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (15,000 GAL. TO LESS THAN 20,000 GAL) | $30.66 | $14.65 | $45.31 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (10,000 GAL. TO LESS THAN 15,000 GAL) | $30.59 | $14.65 | $45.24 |
| TRUCK DRIVER: WATER, FUEL & OIL TANK (1,200 GAL. TO LESS THAN 2,500 GAL) | $27.85 | $14.65 | $42.50 |
| TRUCK DRIVER: TRANSIT MIX (OVER 8 CU. YDS. TO 14 CU. YDS) | $29.72 | $14.65 | $44.37 |
| TRUCK DRIVER: TRANSIT MIX (0 CU. YDS. TO 8 CU. YDS) | $29.62 | $14.65 | $44.27 |
| TRUCK DRIVER: TIREMEN AND GREASER | $30.19 | $14.65 | $44.84 |
| TRUCK DRIVER: OIL SPREADER | $32.68 | $14.65 | $47.33 |
| TRUCK DRIVER: LOWBOY | $32.69 | $14.65 | $47.34 |
| TRUCK DRIVER: FLAT RACK, BULK CEMENT, SEMI-TRAILERS, MUD/BANDING AND PAINT (PICKUP TRUCK) | $29.18 | $14.65 | $43.83 |
| TRUCK DRIVER: FLAT RACK, BULK CEMENT, SEMI-TRAILERS, MUD/BANDING AND PAINT (LESS THAN 10 TONS) | $29.26 | $14.65 | $43.91 |
| TRUCK DRIVER: FLAT RACK, BULK CEMENT, SEMI-TRAILERS, MUD/BANDING AND PAINT (20 TONS AND OVER) | $29.69 | $14.65 | $44.34 |
| TRUCK DRIVER: FLAT RACK, BULK CEMENT, SEMI-TRAILERS, MUD/BANDING AND PAINT (15 TONS TO LESS THAN 20 TONS) | $29.53 | $14.65 | $44.18 |
| TRUCK DRIVER: FLAT RACK, BULK CEMENT, SEMI-TRAILERS, MUD/BANDING AND PAINT (10 TONS TO LESS THAN 15 TONS) | $29.42 | $14.65 | $44.07 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (LESS THAN 8 CU. YDS.) | $29.37 | $14.65 | $44.02 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (95 CU. YDS. TO LESS THAN 105 CU. YDS.) | $30.56 | $14.65 | $45.21 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (8 CU. YDS. TO LESS THAN 14 CU. YDS.) | $29.53 | $14.65 | $44.18 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (75 CU. YDS. TO LESS THAN 95 CU. YDS.) | $30.34 | $14.65 | $44.99 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (55 CU. YDS. TO LESS THAN 75 CU. YDS.) | $30.12 | $14.65 | $44.77 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (35 CU. YDS. TO LESS THAN 55 CU. YDS.) | $29.91 | $14.65 | $44.56 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (14 CU. YDS. TO LESS THAN 35 CU. YDS.) | $29.67 | $14.65 | $44.32 |
| TRUCK DRIVER: DUMP TRUCK, BOTTOM-END OR SIDE (105 CU. YDS. TO LESS THAN 130 CU. YDS.) | $30.69 | $14.65 | $45.34 |
| TRUCK DRIVER: CONCRETE PUMPING | $29.62 | $14.65 | $44.27 |
| TRUCK DRIVER: ARTICULATED | $32.14 | $14.65 | $46.79 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 0 | 01/02/2026 |
| 1 | 05/18/2026 |
Counties Covered
This wage determination applies to 1 county in Utah.
Get notified when UT20260036 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.