AZ20260007
rev 2Heavy
Applies to
Apache, Cochise, Coconino, Gila, Graham, Greenlee, La Paz, Navajo, Santa Cruz, Yavapai
No saved rates yet
Click any row in a trade table to add it here for quick reference.
Get an email when wage determinations covering Yavapai County, Arizona are modified.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Click a row to save its rate for later, then export your selections from the Saved panel.
| Save | Trade & Classification | Rate | Fringe | Total |
|---|---|---|---|---|
| BOILERMAKER Heavy BOIL0627-003 | $36.07 | $30.59 | $66.66 | |
| BRICKLAYER Building BRAZ0003-001 | $32.29 | $9.97 | $42.26 | |
| BRICKLAYER ZONE PAY: Heavy BRAZ0003-005 (RADIUS MILES FROM THE INTERSECTION OF CENTRAL AVE. AND WASHINGTON ST., PHOENIX, AZ) ZONE A: 0-60 MILES- BASE RATE ZONE B: 61-75 MILES- BASE RATE PLUS $2.00 PER HOUR ZONE C: 75-100 MILES- BASE RATE PLUS $3.00 PER HOUR ZONE D: 101-200 MILES- BASE RATE PLUS $3.50 PER HOUR ZONE E: OVER 200 MILES- BASE RATE PLUS $6.50 PER HOUR | $31.68 | $8.90 | $40.58 | |
| BRICKLAYER ZONE PAY: Residential BRAZ0003-007 (RADIUS MILES FROM THE INTERSECTION OF CENTRAL AVE. AND WASHINGTON ST., PHOENIX, AZ) ZONE A: 0-60 MILES- BASE RATE ZONE B: 61-75 MILES- BASE RATE PLUS $2.00 PER HOUR ZONE C: 75-100 MILES- BASE RATE PLUS $3.00 PER HOUR ZONE D: 101-200 MILES- BASE RATE PLUS $3.50 PER HOUR ZONE E: OVER 200 MILES- BASE RATE PLUS $6.50 PER HOUR | $32.29 | $9.97 | $42.26 | |
| CARPENTER Building CARP1912-001 | $33.19 | $19.20 | $52.39 | |
| CARPENTER Highway CARP1912-002 | $35.89 | $14.98 | $50.87 | |
| CARPENTER (INCLUDING FORM WORK) Heavy CARP0408-004 Scope differs by code/WD | $28.08 | $12.74 | $40.82 | |
| CARPENTER (INCLUDING FORM WORK) Heavy CARP0408-004 Scope differs by code/WD | $28.08 | $12.74 | $40.82 | |
| CARPENTER, EXCLUDES DRYWALL HANGING Residential SUAZ2011-005 | $18.16 | 0.00 | $18.16 | |
| CARPENTER: FORMWORK CONCRETE Heavy LABO1184-050 | $31.98 | $9.26 | $41.24 | |
| CEMENT MASON/CONCRETE FINISHER Heavy PLAS0394-005 | $28.78 | $9.17 | $37.95 | |
| CEMENT MASON/CONCRETE FINISHER Residential PLAS0394-006 | $28.78 | $9.17 | $37.95 | |
| CEMENT MASON/CONCRETE FINISHER Building SUAZ2019-006 | $22.00 | 0.00 | $22.00 | |
| CEMENT MASON/CONCRETE FINISHER Highway SUAZ2023-026 | $30.09 | 0.00 | $30.09 | |
| DIVER Heavy CARP1914-002 (WET): ZONE 3 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $48.29 | $8.93 | $57.22 | |
| DIVER Heavy CARP1914-002 (WET): ZONE 2 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $45.17 | $8.93 | $54.10 | |
| DIVER Heavy CARP1914-002 (WET): ZONE 1 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $43.79 | $8.93 | $52.72 | |
| DIVER Heavy CARP1914-002 (STANDBY): ZONE 3 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $28.49 | $8.93 | $37.42 | |
| DIVER Heavy CARP1914-002 (STANDBY): ZONE 2 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $25.37 | $8.93 | $34.30 | |
| DIVER Heavy CARP1914-002 (STANDBY): ZONE 1 ZONE DEFINITIONS: MILEAGE SHALL BE CALCULATED FROM THE CONSTRUCTION SITE TO THE CITY HALL IN PHOENIX OR TUCSON, OR TO THE WORKMEN'S RESIDENCE, WHICHEVER IS LESS: ZONE 1: 0-30 MILES ZONE 2: 31-49 MILES ZONE 3: 50 MILES AND OVER | $22.98 | $8.93 | $31.91 | |
| ELECTRICIAN Heavy ELEC0518-001 (APACHE COUNTY [SOUTH OF HIGHWAY 66]; ALL OF GILA COUNTY; NAVAJO COUNTY [SOUTH AND EAST OF BOUNDARY BEGINNING AT A POINT WHERE CLEAR CREEK CROSSES THE COCONINO-NAVAJO COUNTY LINE, EXTENDING NORTHEASTERLY ALONG CLEAR CREEK AND NORTHEASTERLY TO COTTONWOOD WASH, ALONG COTTONWOOD WASH NORTH EASTERLY TO WHERE IT INTERSECTS THE NAVAJO INDIAN RESERVATION, THEN EAST ALONG THE NAVAJO INDIAN RESERVATION BOUNDARY LINE TO A POINT WHERE IT INTERSECTS THE NAVAJO-APACHE COUNTY LINE]; AND PINAL COU | $36.50 | $14.84 | $51.34 | |
| ELECTRICIAN Heavy ELEC0640-003 (COCONINO AND YAVAPAI COUNTIES; AND THE FOLLOWING PORTIONS OF COUNTIES: NAVAJO COUNTY (NORTH AND WEST OF A BOUNDARY BEGINNING AT A POINT WHERE CLEAR CREEK CROSSES THE COCONINO-NAVAJO COUNTY LINE, NORTHEASTERLY ALONG CLEAR CREEK AND NORTHEASTERLY TO COTTONWOOD WASH, ALONG COTTONWOOD WASH NORTHEASTERLY TO WHERE IT INTERSECTS THE NAVAJO INDIAN RESERVATION THEN EASTERLY ALONG THE NAVAJO INDIAN RESERVATION BOUNDARY LINE TO A POINT WHERE IT INTERSECTS THE NAVAJO-APACHE COUNTY LINE); PINAL | $30.30 | $12.36 | $42.66 | |
| ELECTRICIAN Residential ELEC0518-002 | $17.50 | $7.57 | $25.07 | |
| ELECTRICIAN Building ELEC0640-002 | $39.09 | $15.53 | $54.62 | |
| ELECTRICIAN Highway SUAZ2023-026 | $29.00 | $7.58 | $36.58 | |
| ELECTRICIAN Heavy ELEC0570-014 Scope differs by code/WD | $33.00 | $13.04 | $46.04 | |
| ELECTRICIAN COCHISE, GRAHAM, LA PAZ, AND SANTA CRUZ COUNTIES ZONE DEFINITIONS- ZONE A: THE AREA WITHIN A THIRTY-NINE Heavy ELEC0570-004 (39) MILE RADIUS FROM A BASING POINT AT THE TUCSON TOWN HALL. ZONE B: 40 TO 74 MILE RADIUS FROM THE TOWN HALL IN TUCSON- AN ADDITIONAL $ 3.50 PER HOUR ZONE C: 75 MILE RADIUS FROM THE TOWN HALL IN TUCSON TO THE OUTER LIMITS OF THE GEOGRAPHIC JURISDICTION- AN ADDITIONAL $ 7.50 PER HOUR | $33.00 | $13.04 | $46.04 | |
| ELECTRICIAN: GROUNDPERSON Heavy ELEC0769-003 | $36.00 | $16.88 | $52.88 | |
| ELECTRICIAN: LINE EQUIPMENT OPERATOR Heavy ELEC0769-004 | $46.56 | $19.15 | $65.71 | |
| ELECTRICIAN: LINEPERSON Heavy ELEC0769-001 | $62.08 | $22.49 | $84.57 | |
| ELECTRICIAN/WIREMAN: Heavy ELEC0611-005 (ZONE 1) APACHE COUNTY [AREA NORTH OF HIGHWAY 66] ZONE 1: 0 TO 10 MILES FROM GALLUP, NM ZONE 2: 10 TO 30 MILES FROM GALLUP - ADD 9% ZONE 3: 30 TO 40 MILES FROM GALLUP - ADD 15% ZONE 4: OVER 40 MILES FROM GALLUP - ADD 26% | $40.30 | $13.41 | $53.71 | |
| FORM WORKER Residential SUAZ2011-005 | $14.37 | 0.00 | $14.37 | |
| HVAC MECHANIC (INSTALLATION OF HVAC DUCT) Residential SUAZ2011-005 | $14.13 | 0.00 | $14.13 | |
| IRONWORKER Building IRON0075-012 | $33.00 | $19.91 | $52.91 | |
| IRONWORKER Highway SUAZ2023-026 | $33.15 | $18.57 | $51.72 | |
| IRONWORKER, STRUCTURAL Residential IRON0075-008 | $33.00 | $19.91 | $52.91 | |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR Highway LABO1184-025 | $29.91 | $9.26 | $39.17 | |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR Heavy LABO1184-022 | $29.05 | $9.26 | $38.31 | |
| LABORER: COMMON OR GENERAL Residential SUAZ2011-005 | $10.20 | 0.00 | $10.20 | |
| LABORER: COMMON OR GENERAL Building SUAZ2019-006 | $16.00 | 0.00 | $16.00 | |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) Highway SUAZ2023-026 | $25.22 | $5.08 | $30.30 | |
| LABORER: FENCE ERECTOR Highway LABO1184-017 | $27.41 | $9.26 | $36.67 | |
| LABORER: GENERAL Highway LABO1184-039 | $27.41 | $9.26 | $36.67 | |
| LABORER: GENERAL Heavy SUAZ2023-011 | $24.02 | $3.86 | $27.88 | |
| LABORER: GRADE SETTER Highway LABO1184-018 | $27.41 | $9.26 | $36.67 | |
| LABORER: GRADE SETTER Heavy LABO1184-028 | $29.91 | $9.26 | $39.17 | |
| LABORER: JACKHAMMER Heavy LABO1184-013 | $29.05 | $9.26 | $38.31 | |
| LABORER: LANDSCAPE LABORER Highway SUAZ2023-026 | $18.03 | 0.00 | $18.03 | |
| LABORER: MASON TENDER Highway LABO1184-041 | $27.41 | $9.26 | $36.67 | |
| LABORER: MASON TENDER - BRICK Residential SUAZ2011-005 | $12.77 | 0.00 | $12.77 | |
| LABORER: MASON TENDER - CEMENT/CONCRETE Building SUAZ2019-006 | $18.90 | 0.00 | $18.90 | |
| LABORER: MASON TENDER - CEMENT/CONCRETE/STONE Residential SUAZ2011-005 | $11.00 | 0.00 | $11.00 | |
| LABORER: PIPELAYER Residential SUAZ2011-005 | $13.00 | 0.00 | $13.00 | |
| LABORER: PIPELAYER Building SUAZ2019-006 | $16.77 | $1.05 | $17.82 | |
| LABORER: PIPELAYER Highway SUAZ2023-026 | $25.85 | $7.09 | $32.94 | |
| LABORER: PIPELAYER Heavy LABO1184-014 | $29.91 | $9.26 | $39.17 | |
| OPERATOR: BACKHOE Residential SUAZ2011-005 | $18.29 | 0.00 | $18.29 | |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE Building SUAZ2019-006 | $24.97 | $5.41 | $30.38 | |
| OPERATOR: EXCAVATOR Residential SUAZ2011-005 | $24.67 | 0.00 | $24.67 | |
| OPERATOR: FORKLIFT Residential SUAZ2011-005 | $16.00 | 0.00 | $16.00 | |
| OPERATOR: LOADER (FRONT END) Residential SUAZ2011-005 | $15.00 | 0.00 | $15.00 | |
| OPERATOR: PAVER Residential SUAZ2011-005 (ASPHALT, AGGREGATE, AND CONCRETE) | $20.75 | 0.00 | $20.75 | |
| OPERATOR: ROLLER Residential SUAZ2011-005 | $16.24 | $1.42 | $17.66 | |
| OPERATOR: ROLLER Building SUAZ2019-006 | $23.62 | $6.44 | $30.06 | |
| OPERATOR: SCRAPER Residential SUAZ2011-005 | $19.20 | $1.52 | $20.72 | |
| OPERATOR: TRACTOR Residential SUAZ2011-005 | $20.98 | 0.00 | $20.98 | |
| PAINTER Heavy PAIN0086-004 | $25.47 | $8.00 | $33.47 | |
| PAINTER Building SUAZ2019-006 | $16.48 | 0.00 | $16.48 | |
| PAINTER: BRUSH, ROLLER AND SPRAY Residential SUAZ2011-005 | $13.31 | 0.00 | $13.31 | |
| PAINTER: PAVEMENT MARKING Highway SUAZ2023-026 | $24.60 | $6.34 | $30.94 | |
| PAINTER: SIGN AND DISPLAY ERECTOR Highway SUAZ2023-026 | $18.03 | 0.00 | $18.03 | |
| PILEDRIVERMAN Heavy CARP0408-004 Scope differs by code/WD | $27.38 | $12.44 | $39.82 | |
| PILEDRIVERMAN Heavy CARP0408-004 Scope differs by code/WD | $27.38 | $12.44 | $39.82 | |
| PIPEFITTER Building PLUM0469-010 | $51.15 | $21.00 | $72.15 | |
| PLUMBER Residential SUAZ2011-005 | $20.14 | $4.08 | $24.22 | |
| PLUMBER Building PLUM0469-010 | $51.15 | $21.00 | $72.15 | |
| PLUMBER/PIPEFITTER APACHE, COCONINO,GILA, GREENLEE, LA PAZ, NAVAJO, AND YAVAPAI Heavy PLUM0469-006 | $48.40 | $19.50 | $67.90 | |
| PLUMBER/PIPEFITTER COCHISE AND SANTA CRUZ Heavy PLUM0469-006 | $48.40 | $19.50 | $67.90 | |
| POWER EQUIPMENT OPERATOR: (DRILL RIG/AUGER) Highway ENGI0012-057 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: (DRILL RIG/AUGER) Heavy ENGI0012-048 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: BACKHOE/BACKHOE & LOADER COMBO/TRACK BACKHOE Highway ENGI0012-066 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: BACKHOE/BACKHOE & LOADER COMBO/TRACK BACKHOE Heavy ENGI0012-045 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER Highway ENGI0012-064 | $32.29 | $18.12 | $50.41 | |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER Heavy ENGI0012-044 | $32.29 | $18.12 | $50.41 | |
| POWER EQUIPMENT OPERATOR: BOOM/CRANE TRUCK Highway SUAZ2023-026 | $43.11 | $10.87 | $53.98 | |
| POWER EQUIPMENT OPERATOR: BROOM/SWEEPER Highway SUAZ2023-026 | $26.47 | $7.26 | $33.73 | |
| POWER EQUIPMENT OPERATOR: BULLDOZER Building ENGI0428-017 | $31.69 | $13.52 | $45.21 | |
| POWER EQUIPMENT OPERATOR: BULLDOZER Highway ENGI0012-046 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: BULLDOZER Heavy ENGI0012-046 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: COMPACTOR/ROLLER Highway ENGI0012-067 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: COMPACTOR/ROLLER Heavy ENGI0012-047 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: CONCRETE PUMP TRUCK Highway SUAZ2023-026 | $43.11 | $10.87 | $53.98 | |
| POWER EQUIPMENT OPERATOR: CONCRETE SCREED Highway SUAZ2023-026 | $25.70 | $7.15 | $32.85 | |
| POWER EQUIPMENT OPERATOR: CRANE Building ENGI0428-017 | $36.04 | $13.52 | $49.56 | |
| POWER EQUIPMENT OPERATOR: CRANE/DERRICK Highway ENGI0012-071 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: CRANE/DERRICK Heavy ENGI0012-042 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE Highway ENGI0012-072 (GREATER THAN 1/2 CUBIC YARD) | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE Highway ENGI0012-072 (1/2 CUBIC YARD OR SMALLER) | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: EXCAVATOR/TRACKHOE Heavy ENGI0012-058 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: FIELD EQUIPMENT SERVICEPERSON Highway SUAZ2023-026 | $35.39 | $11.50 | $46.89 | |
| POWER EQUIPMENT OPERATOR: FIELD EQUIPMENT SERVICEPERSON Heavy ENGI0012-037 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: FORKLIFT Highway LABO1184-044 | $30.88 | $9.26 | $40.14 | |
| POWER EQUIPMENT OPERATOR: FORKLIFT Heavy LABO1184-015 | $30.88 | $9.26 | $40.14 | |
| POWER EQUIPMENT OPERATOR: GRADE CHECKER Highway SUAZ2023-026 | $29.74 | $13.07 | $42.81 | |
| POWER EQUIPMENT OPERATOR: GRADE CHECKER Heavy ENGI0012-059 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE Residential ENGI0428-005 | $34.49 | $12.57 | $47.06 | |
| POWER EQUIPMENT OPERATOR: GROUP 1 A-FRAME BOOM TRUCK, WINCH TRUCK, AIR COMPRESSOR, BELTCRETE, BORING BRIDGE AND TEXTURE, CONCRETE MIXER Heavy ENGI0428-002 (SKIP TYPE), CONDUCTOR, BRAKEMAN, HANDLER, CONVEYOR, CROSS TIMING AND PIPE FLOAT, CURING MACHINE, DINKY (UNDER 20 TONS), ELEVATOR HOIST (HUSKY AND SIMILAR), FIREMEN (ALL), FORKLIFT AND ROSS CARRIER, GENERATOR (ALL), HIGHLINE CABLEWAY SIGNALMAN, HYDROGRAPHIC MULCHER, HYDROGRAPHIC SEEDER, JOINT INSERTER, JUMBO FINISHING MACHINE, KOLMAN BELT LOADER, MACHINE CONVEYOR, MULTIPLE POWER CONCRETE SAW, OILER, PAVEMENT BREAKER, POWER GRIZZLY, POWER SWEEPER, PRESSURE GROUT MACHINE, PUMP, ROLLER (EXCEPT AS OTHERWISE CLASSIFIED), SELF-PROPELLED CHIP SPREADING MACHINE, SKIPLOADER (3 CU. YD. AND LESS), SLURRY SEAL MACHINE (MOTO PAVER DRIVER), SMALL SELF-PROPELLED COMPACTOR (WITH BLADE)-BACKFILL, DITCH OPERATION, STRAW BLOWER, TRACTOR (D-5 AND UNDER), TRIPPER, TUGGER, WELDING MACHINE, WHEEL-TYPE TRACTOR (FORD, FERGUSON TYPE WITH ATTACHMENTS, BEE GEE ETC.) | $27.04 | $11.72 | $38.76 | |
| POWER EQUIPMENT OPERATOR: GROUP 2 AGGREGATE PLANT Heavy ENGI0428-002 (INCLUDING CRUSHING, SCREENING AND SAND PLANTS, ETC.), ASPHALT PLANT MIXER, ASPHALT LAYDOWN MACHINE, BACKHOE (RUBBER TIRED OR TRACK, LESS THAN 1 CU. YD. MRC), BEE GEE OPERATOR BORING MACHINE, CONCRETE BATCH PLANT (ALL TYPES AND SIZES), CONCRETE MECHANICAL TAMPING, SPREADING OR FINISHING MACHINE (INCLUDING CLARY, JOHNSON OR SIMILAR TYPES), CONCRETE MIXER (PAVING TYPE AND MOBILE MIXERS), CONCRETE PUMP, CRANE (CRAWLER AND PNEUMATIC LESS THAN 15 TON CAPACITY MRC), DRILLING MACHINE (INCLUDING WATER WELLS), ELEVATING GRADER (ALL TYPES AND SIZES EXCEPT AS OTHERWISE CLASSIFIED), FIELD EQUIPMENT SERVICEMAN, PAVER AND SIMILAR TYPE EQUIPMENT, MOTOR GRADER (ANY TYPE POWER BLADE-ROUGH), OILER DRIVER, OPERATING ENGINEER RIGGER, PNEUMATIC TIRED SCRAPER (ALL SIZES AND TYPES), POWER JUMBO FORM SETTER, ROAD OIL MIXING MACHINE, ROLLER (ON ALL TYPES ASPHALT PAVEMENT), SCREED, SELF-PROPELLED COMPACTOR (WITH BLADE, 815, 825 OR EQUIVALENT-GRADE OPERATION), SKIP LOADER (ALL TYPES WITH A RATED CAPACITY OVER 3 BUT LESS THAN 6 CU. YD.), SLIP FORM (POWER DRIVEN LIFTING DEVICE FOR CONCRETE FORMS), SOIL CEMENT ROAD MIXINGMACHINE (SINGLE PASS TYPE), HEATER AND PLANER, TRACTOR (DOZER, PUSHER-ALL), TRAVELING PIPE-WRAPPING MACHINE, TRENCHING MACHINE, TUGGER (TWO OR MORE) | $30.31 | $11.72 | $42.03 | |
| POWER EQUIPMENT OPERATOR: GROUP 3 ASPHALT OR CONCRETE PLANING, ROTOMILL AND MILLING MACHINE, AUTO GRADE MACHINE Heavy ENGI0428-002 (CMI AND SIMILAR EQUIPMENT), BORING MACHINE (INCLUDING MOLE, BADGER AND SIMILAR TYPE), CONCRETE PUMP (TRUCK MOUNTED WITH BOOM), CRANE (CRAWLER AND PNEUMATIC OVER 15 TONS BUT LESS THAN 100 TONS CAPACITY MRC), CRAWLER TYPE TRACTOR WITH BOOM ATTACHMENT AND SLOPE BAR, DERRICK, GRADALL, HEAVY DUTY MECHANIC/WELDER, HELICOPTER HOIST OPERATOR OR PILOT, HIGHLINE CABLEWAY, MASS EXCAVATOR (150 BUCYRUS, ERIE AND SIMILAR TYPE), MECHANICAL HOIST (TWO OR MORE DRUMS), MOTOR GRADER (ANY TYPE POWER BLADE-FINISH), MUCKING MACHINE, OVERHEAD CRANE, GRADE CHECKER, PILEDRIVER ENGINEER (PORTABLE, STATIONARY OR SKID RIG), POWER DRIVEN DITCH LINING OR DITCH TRIMMING MACHINE, REMOTE CONTROL EARTH MOVING MACHINE, SKIP LOADER (ALL TYPES WITH RATED CAPACITY 6 CU. YD. BUT LESS THAN 10 CU. YD.), SLIP FORM PAVING MACHINE (INCLUDING GUNNERT, ZIMMERMAN AND SIMILAR TYPES), TOWER CRANE OR SIMILAR TYPE, UNIVERSAL EQUIPMENT OPERATOR (BACKHOE, CLAMSHELL, DRAGLINE, SHOVEL ETC., UP TO 10 CU. YD.); OPERATING ENGINEERS ELECTRICIAN INCLUDING TOWER ERECTOR, LINEMAN & CABLE SPLICER (LOAD SIDE OF MAIN DISCONNECT) | $31.39 | $11.72 | $43.11 | |
| POWER EQUIPMENT OPERATOR: GROUP 4 CRANE OPERATOR Heavy ENGI0428-002 (PNEUMATIC OR CRAWLER-100 TONS HOISTING CAPACITY AND OVER, MRC RATING), SKIP LOADER (ALL TYPES WITH RATED CAPACITY OF 10 CU. YD. OR MORE), UNIVERSAL EQUIPMENT OPERATOR (BACKHOE, CLAMSHELL, DRAGLINE, SHOVEL, ETC., 10 CU. YD. AND OVER) MULTIPLE-UNIT EARTH EQUIPMENT (HOLLAND LOADER ETC.), TRACTOR OPERATOR, PNEUMATIC-TIRED OR TRACK TYPE, TWO UNITS-$0.50 PER HOUR OVER BASE RATE; AND $1.00 PER HOUR FOR EACH ADDITIONAL UNIT ALL OPERATORS, OILERS, AND MOTOR CRANE DRIVERS ON EQUIPMENT WITH BOOMS, EXCEPT CONCRETE PUMPING TRUCK BOOMS, INCLUDING JIBS, SHALL RECEIVE $0.01 PER HOUR PER FOOT OVER 80 FT IN ADDITION TO REGULAR RATE OF PAY PREMIUM PAY FOR PERFORMING HAZARDOUS WASTE REMOVAL $0.50 PER HOUR OVER BASE RATE | $32.42 | $11.72 | $44.14 | |
| POWER EQUIPMENT OPERATOR: HORIZONTAL DIRECTIONAL DRILL Highway LABO1184-016 | $31.98 | $9.26 | $41.24 | |
| POWER EQUIPMENT OPERATOR: HORIZONTAL DIRECTIONAL DRILL Heavy LABO1184-016 | $31.98 | $9.26 | $41.24 | |
| POWER EQUIPMENT OPERATOR: LOADER Building ENGI0428-017 | $34.96 | $13.52 | $48.48 | |
| POWER EQUIPMENT OPERATOR: LOADER/FRONT END LOADER Highway ENGI0012-069 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: LOADER/FRONT END LOADER Heavy ENGI0012-049 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: MECHANIC Highway ENGI0012-075 | $37.67 | $18.12 | $55.79 | |
| POWER EQUIPMENT OPERATOR: MECHANIC Heavy ENGI0012-043 | $37.67 | $18.12 | $55.79 | |
| POWER EQUIPMENT OPERATOR: MILLING MACHINE Highway SUAZ2023-026 | $30.09 | $6.45 | $36.54 | |
| POWER EQUIPMENT OPERATOR: MOTOR GRADER/BLADE Highway ENGI0012-074 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: MOTOR GRADER/BLADE Heavy ENGI0012-061 | $36.64 | $18.12 | $54.76 | |
| POWER EQUIPMENT OPERATOR: OILER Highway SUAZ2023-026 | $31.56 | $10.69 | $42.25 | |
| POWER EQUIPMENT OPERATOR: OILER Heavy ENGI0012-035 | $32.29 | $18.12 | $50.41 | |
| POWER EQUIPMENT OPERATOR: PAVER/SPREADER/FINISH EQUIPMENT (ASPHALT, AGGREGATE, & CONCRETE) Highway ENGI0012-051 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: SCRAPER Highway ENGI0012-052 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: SCRAPER Heavy SUAZ2023-011 | $32.41 | 0.00 | $32.41 | |
| POWER EQUIPMENT OPERATOR: TRACTOR Highway ENGI0012-053 | $35.56 | $18.12 | $53.68 | |
| POWER EQUIPMENT OPERATOR: TRENCHER Highway LABO1184-033 | $30.88 | $9.26 | $40.14 | |
| POWER EQUIPMENT OPERATOR: TRENCHER Heavy ENGI0012-054 | $35.56 | $18.12 | $53.68 | |
| ROOFER Residential SUAZ2011-005 | $13.67 | 0.00 | $13.67 | |
| SHEET METAL WORKER Building SHEE0359-001 | $49.39 | $19.86 | $69.25 | |
| TILE SETTER Building SUAZ2019-006 | $21.50 | 0.00 | $21.50 | |
| TRAFFIC CONTROL Highway LABO1184-021 | $27.41 | $9.26 | $36.67 | |
| TRAFFIC CONTROL Heavy LABO1184-042 | $27.41 | $9.26 | $36.67 | |
| TRUCK DRIVER GROUP 2: 2 OR 3 AXLE DUMP , WATER TRUCK UNDER 2500 GAL. FOOTNOTE: HEALTH & WELFARE AS OF SEPTEMBER 1, 2024 Heavy TEAM0104-002 | $26.95 | $1.65 | $28.60 | |
| TRUCK DRIVER GROUP 3- 4 AXLE DUMP, WATER TRUCK DRIVE- Heavy TEAM0104-002 (2500 GAL BUT LESS THAN 4000 GAL) FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 | $27.43 | $1.65 | $29.08 | |
| TRUCK DRIVER GROUP 4- 5 AXLE DUMP, WATER TRUCK 4000 GAL AND OVER FOOTNOTE: HEALTH & WELFARE AS OF SEPTEMBER 1, 2024 Heavy TEAM0104-002 | $28.68 | $1.65 | $30.33 | |
| TRUCK DRIVER GROUP 5- 6-AXLE DUMP FOOTNOTE: HEALTH & WELFARE $1,330.26 PER MONTH IN ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 Heavy TEAM0104-002 | $27.80 | $1.65 | $29.45 | |
| TRUCK DRIVER GROUP 6- 7-AXLE DUMP, 8-AXLE DUMP ADDITIONAL FRINGE BENEFITS. AS OF SEPTEMBER 1, 2024 Heavy TEAM0104-002 | $29.47 | $1.65 | $31.12 | |
| TRUCK DRIVER: CONCRETE Highway LABO1184-047 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: CONCRETE Heavy LABO1184-034 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: DUMP Highway LABO1184-048 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: DUMP Heavy LABO1184-035 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: DUMP TRUCK Residential SUAZ2011-005 | $17.02 | 0.00 | $17.02 | |
| TRUCK DRIVER: HYDROVAC Heavy ENGI0012-055 | $35.56 | $18.12 | $53.68 | |
| TRUCK DRIVER: OFF ROAD TRUCK Highway ENGI0012-070 | $35.56 | $18.12 | $53.68 | |
| TRUCK DRIVER: OIL DISTRIBUTOR Highway SUAZ2023-026 | $29.75 | $8.04 | $37.79 | |
| TRUCK DRIVER: SWEEPER Highway SUAZ2023-026 | $20.24 | $5.48 | $25.72 | |
| TRUCK DRIVER: WATER Highway LABO1184-049 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: WATER Heavy LABO1184-036 | $30.88 | $9.26 | $40.14 | |
| TRUCK DRIVER: WATER TRUCK Residential SUAZ2011-005 | $14.50 | 0.00 | $14.50 |
No trade rates match your search and filter selection.
Heavy
Applies to
Apache, Cochise, Coconino, Gila, Graham, Greenlee, La Paz, Navajo, Santa Cruz, Yavapai
Residential
Applies to
Coconino, Yavapai
Building
Applies to
Coconino, Mohave, Yavapai
Highway
Heavy