MA20260010
HeavyDavis-Bacon Act general wage determination for heavy construction in Massachusetts.
Track MA20260010
Get an email when this wage determination gets a new modification.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Wage Rates
Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.
BOIL0029-001 Effective 01/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BOILERMAKER | $50.62 | $28.82 | $79.44 |
BRMA0001-005 Effective 08/01/2023 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD CHAPTER) | $50.81 | $32.27 | $83.08 |
BRMA0001-007 Effective 08/01/2023 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| BRICKLAYER: BRICKLAYERS; CEMENT MASONS; PLASTERERS; STONE MASONS; MARBLE, TILE & TERRAZZO WORKERS (SPRINGFIELD/PITTSFIELD CHAPTER BERKSHIRE COUNTY) | $50.81 | $32.27 | $83.08 |
CARP0056-004 Effective 08/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| DIVER TENDER | $61.70 | $35.47 | $97.17 |
| DIVER | $78.11 | $35.47 | $113.58 |
CARP0056-009 Effective 08/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PILEDRIVERMAN | $51.97 | $35.47 | $87.44 |
CARP0336-005 Effective 09/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (FRANKLIN COUNTY (ERVING, ORANGE, NORTH ORANGE, AND WARWICK)) | $43.33 | $27.82 | $71.15 |
CARP0336-010 Effective 09/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (BERKSHIRE) | $43.33 | $27.82 | $71.15 |
CARP0336-012 Effective 09/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (HAMPDEN; HAMPSHIRE; AND FRANKLIN (REMAINDER OF COUNTY)) | $43.33 | $27.82 | $71.15 |
CARP1121-004 Effective 04/21/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| MILLWRIGHT | $43.42 | $33.00 | $76.42 |
ELEC0007-002 Effective 06/29/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (HAMPDEN (EXCEPT CHESTER & HOLYOKE); HAMPSHIRE (BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
ELEC0007-003 Effective 06/29/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| ELECTRICIAN (BERKSHIRE; FRANKLIN; HAMPDEN (CHESTER, HOLYOKE); HAMPSHIRE (EXCEPT BELCHERTOWN, WARE)) | $52.16 | $29.56 | $81.72 |
ENGI0098-007 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| POWER EQUIPMENT OPERATORS: GROUP 6 COMPRESSOR (ONE OR TWO) 315 CU FT TO 900 CU FT; PUMPS 4 INCHES TO 16 INCHES (TOTAL DISCHARGE). HAZARDOUS WASTE PREMIUM $2.00 FOOTNOTE FOR POWER EQUIPMENT OPERATORS: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $36.06 | $31.04 | $67.10 |
| POWER EQUIPMENT OPERATORS: GROUP 3 COMBINATION BACKHOE/LOADER UP TO 3/4 CU YD; SCRAPERS UP TO 21 CU YD (STRUCK LOAD, SELF PROPELLED OR TRACTOR DRAWN); TIREMAN; FRONT END LOADERS UP TO 4 YDS; WELL DRILLERS; ENGINEER OR FIREMAN ON HIGH PRESSURE BOILER; SELF-LOADING BATCH PLANT; WELL POINT OPERATORS ELECTRIC PUMPS USED IN WELL POINT SYSTEM; PUMPS, 16 INCHES AND OVER (TOTAL DISCHARGE); COMPRESSOR, ONE OR TWO 900 CU FT AND OVER; POWERED GREASE TRUCK; TUNNEL LOCOMOTIVES AND DINGYS; GROUT PUMPS; HYDRAULIC JACKS; BOOM TRUCK; HYDRAULIC CRANES- UP TO 10 TON. HAZARDOUS WASTE PREMIUM A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.35 | $31.04 | $73.39 |
| POWER EQUIPMENT OPERATORS: GROUP 2 ROTARY DRILL WITH MOUNTED COMPRESSOR; COMPRESSOR HOUSE (3 TO 6 COMPRESSORS); ROCK AND EARTH BORING MACHINES (EXCLUDING MCCARTHY AND SIMILAR DRILLS); FRONT END LOADERS 4 CU YDS TO 5 1/2 CU YDS); FORKLIFTS-7 FT LIFT AND OVER 3 TON CAPACITY; SCRAPER 21 YDS AND OVER (STRUCK LOAD); SONIC HAMMER CONSOLE; RECLAIMERS ROAD PLANER/MILLING MACHINE; CAL TRACKS; BALLAST REGULATORS; RAIL ANCHOR MACHINES; SWITCH TAMPERS, ASPHALT PAVERS; MECHANIC; WELDER AND TRANSFER MACHINE. HAZARDOUS WASTE PREMIUM $2.00 HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, COLUMBUS DAY, VETERANS DAY, THANKSGIVING DAY AND CHRISTMAS DAY | $42.57 | $31.04 | $73.61 |
IRON0007-014 Effective 09/16/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER (BERKSHIRE (BECKET, EAST OTIS, HINSDALE, MONTEREY, NEW MARLBORO, NORTH OTIS, OTIS, PERU, SANDISFIELD, SAVOY, SHEFFIELD, WASHINGTON, WINDSOR); FRANKLIN; HAMPDEN; HAMPSHIRE) | $41.89 | $33.90 | $75.79 |
IRON0012-003 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER (BERKSHIRE (LEE)) | $40.75 | $31.91 | $72.66 |
IRON0012-004 Effective 07/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKERS: STRUCTURAL, ORNAMENTAL, REINFORCING, FENCE ERECTOR, MACHINERY MOVER, RIGGER, RODMAN, STONE DERRICKMAN (BERKSHIRE (REMAINDER OF COUNTY)) | $40.75 | $31.91 | $72.66 |
| IRONWORKERS: SHEETER (BERKSHIRE (REMAINDER OF COUNTY)) | $41.00 | $31.91 | $72.91 |
LABO0022-002 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (ORANGE, WARWICK)) | $40.95 | $29.70 | $70.65 |
| LABORERS: GROUP 5 PRECAST FLOOR AND ROOF, PLANK ERECTOR (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 |
| LABORERS: GROUP 4 BLASTER; POWDERMAN (FRANKLIN (ORANGE, WARWICK)) | $39.95 | $29.70 | $69.65 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR; BLOCK PAVER; RAMMER; CURB SETTER, HYDRAULIC AND SIMILAR SELF-POWERED DRILLS (FRANKLIN (ORANGE, WARWICK)) | $39.70 | $29.70 | $69.40 |
| LABORERS: GROUP 1 LABORERS; CARPENTER TENDERS; CEMENT FINISHER TENDERS, PLASTERER TENDERS (FRANKLIN (ORANGE, WARWICK)) | $38.95 | $29.70 | $68.65 |
LABO0473-005 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 5 FLAGGERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $27.01 | $29.70 | $56.71 |
| LABORERS: GROUP 4 BLASTERS, POWDERMEN (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR, BLOCK PAVERS, RAMMERS, CURB SETTERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
| LABORERS: GROUP 1 CARPENTER TENDERS, CEMENT FINISHER TENDERS, LABORERS, WRECKING LABORERS (FRANKLIN (EXCEPT ORANGE AND WARRICK); HAMPDEN AND HAMPSHIRE COUNTIES (WITH THE EXCEPTION OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON)) | $35.00 | $29.70 | $64.70 |
LABO0473-006 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: GROUP 6 ASBESTOS ABATEMENT, TOXIC AND HAZARDOUS WASTE LABORERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 5 FLAGGERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $27.01 | $26.65 | $53.66 |
| LABORERS: GROUP 4 BLASTERS, POWDERMEN (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 3 AIR TRACK OPERATOR, BLOCK PAVERS, RAMMERS, CURB SETTERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
| LABORERS: GROUP 1 CARPENTER TENDERS, CEMENT FINISHER TENDERS, LABORERS, WRECKING LABORERS (BERKSHIRE; HAMPSHIRE COUNTIES (THE TOWNS OF CHESTERFIELD, CUMMINGTON, GOSHEN, MIDDLEFIELD, PLAINFIELD, AND WORTHINGTON ONLY)) | $33.99 | $26.65 | $60.64 |
LABO1421-002 Effective 12/02/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORERS: GROUP 6 ASBESTOS, LEAD PAINT, TOXIC AND HAZARDOUS WASTE | $46.25 | $29.70 | $75.95 |
| LABORERS: GROUP 5 YARDMAN, BURNERS, SAWYERS | $45.35 | $29.70 | $75.05 |
| LABORERS: GROUP 4 YARDMAN (SALVAGE YARD ONLY) | $42.25 | $29.70 | $71.95 |
| LABORERS: GROUP 3 SMALL BACKHOES, LOADERS ON TRACKS, BOBCAT TYPE LOADERS, HYDRAULIC ""BROCK"" TYPE HAMMER OPERATORS, CONCRETE CUTTING SAWS | $47.25 | $29.70 | $76.95 |
| LABORERS: GROUP 2 BURNERS, JACKHAMMERS | $47.00 | $29.70 | $76.70 |
| LABORERS: GROUP 1 ADZEMAN, WRECKING LABORER | $46.25 | $29.70 | $75.95 |
PAIN0035-010 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PAINTER: SPRAY, SANDBLAST (NEW CONSTRUCTION) | $39.48 | $31.85 | $71.33 |
| PAINTER: BRUSH, TAPER (NEW CONSTRUCTION) | $38.78 | $31.85 | $70.63 |
| PAINTER REPAINT: SPRAY, SANDBLAST | $36.80 | $31.85 | $68.65 |
| PAINTER REPAINT: BRUSH, TAPER | $35.40 | $31.85 | $67.25 |
| PAINTER REPAINT: BRIDGE | $56.76 | $31.85 | $88.61 |
PLUM0004-003 Effective 09/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER AND STEAMFITTER (FRANKLIN (ORANGE)) | $55.00 | $31.57 | $86.57 |
PLUM0104-004 Effective 09/17/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBERS AND PIPEFITTERS (BERKSHIRE (BECKET, OTIS, SANDISFIELD); FRANKLIN (EXCEPT MONROE, ROWE, AND THE WESTERN PART OF CHARLEMONT); HAMPDEN; HAMPSHIRE) | $52.26 | $31.05 | $83.31 |
PLUM0104-009 Effective 09/17/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PLUMBER AND STEAMFITTER (BERKSHIRE (EXCEPT OTIS, BECKET, SANDISFIELD); FRANKLIN (MONROE, ROWE AND THE WESTERN PART OF CHARLEMONT)) | $52.26 | $31.05 | $83.31 |
TEAM0379-001 Effective 06/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVERS: GROUP 7 TRAILERS FOR EARTH MOVING EQUIPMENT (DOUBLE HOOKUP) POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.82 | $37.35 | $79.17 |
| TRUCK DRIVERS: GROUP 6 SPECIALIZED EARTH MOVING EQUIPMENT OVER 35 TONS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.53 | $37.35 | $78.88 |
| TRUCK DRIVERS: GROUP 4 FOUR AND FIVE AXLE EQUIPMENT POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.14 | $37.35 | $78.49 |
| TRUCK DRIVERS: GROUP 3 THREE AXLE EQUIPMENT AND TIREMAN POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $41.02 | $37.35 | $78.37 |
| TRUCK DRIVERS: GROUP 2 TWO AXLE EQUIPMENT; & FORKLIFT OPERATOR POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM FOOTNOTES: A. PAID HOLIDAYS: NEW YEAR'S DAY, WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.95 | $37.35 | $78.30 |
| TRUCK DRIVERS: GROUP 1 STATION WAGONS; PANEL TRUCKS; AND PICKUP TRUCKS POWER TRUCKS $.25 DIFFERENTIAL BY AXLE TUNNEL WORK (UNDERGROUND ONLY) $.40 DIFFERENTIAL BY AXLE HAZARDOUS MATERIALS (IN HOT ZONE ONLY) $2.00 PREMIUM WASHINGTON'S BIRTHDAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, PATRIOT'S DAY, COLUMBUS DAY, VETERAN'S DAY, THANKSGIVING DAY AND CHRISTMAS DAY B. PAID VACATION: EMPLOYEES WITH 4 MONTHS TO 1 YEAR OF SERVICE RECEIVE 1/2 DAY'S PAY PER MONTH; 1 WEEK VACATION FOR 1 - 5 YEARS OF SERVICE; 2 WEEKS VACATION FOR 5 - 10 YEARS OF SERVICE; AND 3 WEEKS VACATION FOR MORE THAN 10 YEARS OF SERVICE | $40.78 | $37.35 | $78.13 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 0 | 01/02/2026 |
| 1 | 05/18/2026 |
Counties Covered
This wage determination applies to 4 counties in Massachusetts.
Get notified when MA20260010 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.