CARP0330-003 Effective 09/01/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| CARPENTER (INCLUDES FORM WORK) | $50.10 | $31.45 | $81.55 |
IRON0007-026 Effective 09/16/2025 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| IRONWORKER: ORNAMENTAL AND STRUCTURAL | $57.87 | $37.67 | $95.54 |
LABO0133-001 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER: CONCRETE SURFACER | $46.20 | $29.85 | $76.05 |
LABO0385-002 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER LANDSCAPE | $38.95 | $29.41 | $68.36 |
LABO0385-003 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER: FENCE ERECTION | $38.95 | $29.41 | $68.36 |
LABO0721-002 Effective 12/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER: GUARDRAIL INSTALLATION | $38.95 | $29.81 | $68.76 |
LABO0876-001 Effective 06/01/2018 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| LABORER (COMMON OR GENERAL) | $33.25 | $22.92 | $56.17 |
PAIN0035-023 Effective 07/01/2024 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| PAINTER: STEEL | $56.76 | $36.00 | $92.76 |
SUMA2014-013 Effective 01/11/2017 | Trade | Rate | Fringe | Total |
|---|---|---|---|
| TRUCK DRIVER: FLATBED TRUCK | $48.53 | $0.00 | $48.53 |
| TRUCK DRIVER: DUMP TRUCK | $37.35 | $11.00 | $48.35 |
| TRUCK DRIVER: CONCRETE TRUCK | $33.69 | $15.79 | $49.48 |
| TRAFFIC CONTROL: LABORER-CONES/ BARRICADES/BARRELS - SETTER/MOVER/SWEEPER | $53.35 | $12.78 | $66.13 |
| TRAFFIC CONTROL: FLAGGER | $23.00 | $20.44 | $43.44 |
| PAINTER: SPRAY (LINESTRIPING) | $47.30 | $6.42 | $53.72 |
| OPERATOR: PILEDRIVER | $42.56 | $17.34 | $59.90 |
| OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) | $41.63 | $23.04 | $64.67 |
| OPERATOR: MECHANIC | $48.74 | $11.79 | $60.53 |
| OPERATOR: FORKLIFT | $64.67 | $0.00 | $64.67 |
| LABORER: JACK HAMMER | $38.69 | $17.33 | $56.02 |
| LABORER: CONCRETE SAW (HAND HELD/WALK BEHIND) | $44.43 | $14.18 | $58.61 |
| LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR | $34.32 | $17.35 | $51.67 |
| IRONWORKER, REINFORCING | $44.52 | $19.36 | $63.88 |
| ELECTRICIAN, INCLUDES TRAFFIC SIGNALIZATION | $45.13 | $13.86 | $58.99 |
| CEMENT MASON/CONCRETE FINISHER | $56.70 | $21.08 | $77.78 |
No trade rates match your search.
Modification History
| Modification | Publication Date |
|---|---|
| 0 | 01/02/2026 |
| 1 | 05/18/2026 |
Counties Covered
This wage determination applies to 1 county in Massachusetts.
Get notified when MA20260023 is modified
This determination has been revised 2 times. We'll email you when a new modification is published.
Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.
Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.