MI20260122

Building

Davis-Bacon Act general wage determination for building construction in Michigan.

Modification 0, revised 05/18/2026 52 trade rates 1 county View on SAM.gov

Track MI20260122

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0047-005 Effective 07/01/2025
Trade Rate Fringe Total
ASBESTOS WORKER/HEAT & FROST INSULATOR $40.00 $23.65 $63.65
BOIL0169-002 Effective 07/01/2025
Trade Rate Fringe Total
BOILERMAKER $43.50 $37.64 $81.14
BRMI0009-019 Effective 08/01/2024
Trade Rate Fringe Total
TILE SETTER $31.43 $21.13 $52.56
PLASTERER $33.09 $26.58 $59.67
TILE SETTER $31.43 $21.13 $52.56
PLASTERER $33.09 $26.58 $59.67
BRMI0009-019 Effective 09/01/2024
Trade Rate Fringe Total
TILE SETTER $31.43 $21.13 $52.56
PLASTERER $33.09 $26.58 $59.67
TILE SETTER $31.43 $21.13 $52.56
PLASTERER $33.09 $26.58 $59.67
CARP0706-008 Effective 06/01/2025
Trade Rate Fringe Total
CARPENTER (ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, AND METAL STUD INSTALLATION) $35.86 $23.69 $59.55
CARP1102-003 Effective 06/01/2025
Trade Rate Fringe Total
MILLWRIGHT $42.92 $39.13 $82.05
ELEC0557-003 Effective 06/01/2020
Trade Rate Fringe Total
ELECTRICIAN: EXCLUDES LOW VOLTAGE WIRING (TOWNSHIPS OF ARCADA, BETHANY, ELBA, EMERSON, HAMILTON, LAFAYETTE, NEW HAVEN, NEWARK, NORTH STAR, PINE RIVER, SEVILLE, SUMNER, WASHINGTON, & WHEELER) $34.25 $23.13 $57.38
ENGI0324-024 Effective 06/01/2024
Trade Rate Fringe Total
OPERATOR: POWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $33.71 $25.25 $58.96
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $39.57 $25.25 $64.82
IRON0025-009 Effective 04/01/2025
Trade Rate Fringe Total
IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) $30.02 $27.43 $57.45
IRON0025-010 Effective 06/01/2025
Trade Rate Fringe Total
IRONWORKER, STRUCTURAL $36.55 $35.93 $72.48
IRONWORKER, REINFORCING $36.55 $33.37 $69.92
LABO1098-030 Effective 07/01/2025
Trade Rate Fringe Total
LABORER: SANDBLASTER $28.21 $13.45 $41.66
LABORER: MASON TENDER - CEMENT/CONCRETE AND PIPELAYER $27.68 $13.45 $41.13
PAIN1803-001 Effective 06/01/2025
Trade Rate Fringe Total
PAINTER: DRYWALL FINISHING/TAPING $30.22 $22.22 $52.44
PAINTER: BRUSH, ROLLER AND SPRAY $29.23 $19.11 $48.34
PLAS0016-038 Effective 04/01/2014
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $25.47 $12.38 $37.85
PLUM0085-004 Effective 05/04/2023
Trade Rate Fringe Total
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) $43.50 $22.10 $65.60
PIPEFITTER (HVAC PIPE INSTALLATION ONLY) $45.50 $21.75 $67.25
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) $45.50 $21.75 $67.25
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) $43.50 $22.10 $65.60
PIPEFITTER (HVAC PIPE INSTALLATION ONLY) $45.50 $21.75 $67.25
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) $45.50 $21.75 $67.25
PLUM0085-004 Effective 05/01/2024
Trade Rate Fringe Total
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) $43.50 $22.10 $65.60
PIPEFITTER (HVAC PIPE INSTALLATION ONLY) $45.50 $21.75 $67.25
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) $45.50 $21.75 $67.25
PLUMBER (EXCLUDING HVAC PIPE AND SYSTEM INSTALLATION) $43.50 $22.10 $65.60
PIPEFITTER (HVAC PIPE INSTALLATION ONLY) $45.50 $21.75 $67.25
PIPEFITTER (EXCLUDES HVAC PIPE AND SYSTEM INSTALLATION) $45.50 $21.75 $67.25
SFMI0669-003 Effective 01/02/2025
Trade Rate Fringe Total
SPRINKLER FITTER (FIRE SPRINKLERS) $41.34 $27.39 $68.73
SHEE0007-021 Effective 05/01/2018
Trade Rate Fringe Total
SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) $26.83 $23.78 $50.61
SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) $26.83 $23.78 $50.61
SUMI2011-047 Effective 02/14/2011
Trade Rate Fringe Total
TRUCK DRIVER: FLATBED TRUCK $16.80 $3.97 $20.77
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $15.65 $3.12 $18.77
ROOFER $15.73 $7.41 $23.14
OPERATOR: TRACTOR $19.60 $7.31 $26.91
OPERATOR: ROLLER $28.02 $7.07 $35.09
OPERATOR: GRADER/BLADE $24.04 $6.03 $30.07
OPERATOR: BULLDOZER $22.34 $1.22 $23.56
LABORER: MASON TENDER - BRICK $15.03 $3.10 $18.13
LABORER: LANDSCAPE & IRRIGATION $12.84 $0.00 $12.84
LABORER: COMMON OR GENERAL $10.70 $1.22 $11.92
GLAZIER $16.95 $4.74 $21.69
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYING-CARPET $15.80 $1.22 $17.02
CARPENTER (FLOOR LAYING-CARPET ONLY) $19.59 $7.57 $27.16
BRICKLAYER $22.20 $3.10 $25.30

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in Michigan.

Get notified when MI20260122 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.