Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

BOIL0169-002 Effective 07/01/2025
Trade Rate Fringe Total
BOILERMAKER $43.50 $37.64 $81.14
BRMI0001-005 Effective 06/01/2022
Trade Rate Fringe Total
TILE SETTER $37.88 $22.67 $60.55
BRICKLAYER $38.87 $25.18 $64.05
CARP0687-010 Effective 06/01/2025
Trade Rate Fringe Total
CARPENTER (ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION) $42.44 $31.43 $73.87
CARP1102-003 Effective 06/01/2025
Trade Rate Fringe Total
MILLWRIGHT $42.92 $39.13 $82.05
ELEC0058-005 Effective 07/02/2021
Trade Rate Fringe Total
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (TECHNICIAN) $37.62 $14.80 $52.42
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (INSTALLER) $30.12 $14.57 $44.69
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) $51.32 $28.44 $79.76
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (TECHNICIAN) $37.62 $14.80 $52.42
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (INSTALLER) $30.12 $14.57 $44.69
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) $51.32 $28.44 $79.76
ELEC0058-005 Effective 06/28/2024
Trade Rate Fringe Total
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (TECHNICIAN) $37.62 $14.80 $52.42
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (INSTALLER) $30.12 $14.57 $44.69
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) $51.32 $28.44 $79.76
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (TECHNICIAN) $37.62 $14.80 $52.42
ELECTRICIAN, LOW VOLTAGE WIRING ONLY (INSTALLER) $30.12 $14.57 $44.69
ELECTRICIAN (EXCLUDES LOW VOLTAGE WIRING) $51.32 $28.44 $79.76
ENGI0324-023 Effective 06/01/2022
Trade Rate Fringe Total
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL D) $39.08 $24.85 $63.93
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL D WHEN CAPPING LANDFILL) $36.43 $24.85 $61.28
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL B AND C) $44.13 $24.85 $68.98
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 2 (AREA 2: LEVEL A) $26.38 $24.85 $51.23
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL D) $26.38 $24.85 $51.23
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL B AND C) $30.61 $24.85 $55.46
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: GROUP 1 (AREA 2: LEVEL A) $39.08 $24.85 $63.93
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D) $34.72 $24.85 $59.57
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL B AND C) $36.47 $24.85 $61.32
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL A) $34.72 $24.85 $59.57
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL B AND C) $26.13 $24.85 $50.98
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 2: LEVEL A) $42.38 $24.85 $67.23
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL D) $39.08 $24.85 $63.93
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) $30.61 $24.85 $55.46
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL B AND C) $36.47 $24.85 $61.32
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 2 (AREA 1: LEVEL A) $36.43 $24.85 $61.28
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL D) $38.18 $24.85 $63.03
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL D WHEN CAPPING LANDFILL) $28.86 $24.85 $53.71
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL B AND C) $44.13 $24.85 $68.98
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: GROUP 1 (AREA 1: LEVEL A) $40.83 $24.85 $65.68
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D) $34.72 $24.85 $59.57
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) $44.13 $24.85 $68.98
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL B AND C) $26.13 $24.85 $50.98
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 1: LEVEL A) $42.38 $24.85 $67.23
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D) $42.38 $24.85 $67.23
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL D WHEN CAPPING LANDFILL) $36.47 $24.85 $61.32
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL B AND C) $40.83 $24.85 $65.68
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 1: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 140' OR LONGER (AREA 1: LEVEL A) $28.86 $24.85 $53.71
OPERATOR: POWER EQUIPMENT: GROUP 5 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. $30.61 $24.85 $55.46
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; FORK TRUCK (OVER 20' LIFT) CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY. $36.47 $24.85 $61.32
IRON0025-009 Effective 04/01/2025
Trade Rate Fringe Total
IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) $30.02 $27.43 $57.45
IRON0025-010 Effective 06/01/2025
Trade Rate Fringe Total
IRONWORKER, STRUCTURAL $36.55 $35.93 $72.48
IRONWORKER, REINFORCING $36.55 $33.37 $69.92
LABO1075-013 Effective 06/01/2025
Trade Rate Fringe Total
LABORER: COMMON OR GENERAL; MASON TENDER - BRICK; PIPELAYER; AND SANDBLASTER EXCLUDES OPEN CUT CONSTRUCTION $31.30 $18.40 $49.70
PAIN1474-007 Effective 06/01/2010
Trade Rate Fringe Total
PAINTER: DRYWALL FINISHING/TAPING $23.79 $12.02 $35.81
PAINTER: BRUSH, ROLLER AND SPRAY $23.79 $12.02 $35.81
PLAS0067-005 Effective 04/01/2014
Trade Rate Fringe Total
PLASTERER $30.63 $14.07 $44.70
PLUM0636-011 Effective 06/05/2024
Trade Rate Fringe Total
PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION; EXCLUDES HVAC SYSTEM INSTALLATION) $40.30 $38.80 $79.10
SFMI0669-003 Effective 01/02/2025
Trade Rate Fringe Total
SPRINKLER FITTER (FIRE SPRINKLERS) $41.34 $27.39 $68.73
SHEE0080-007 Effective 06/01/2024
Trade Rate Fringe Total
SHEET METAL WORKER (HVAC DUCT & SYSTEM INSTALLATION) $42.51 $35.77 $78.28
SHEET METAL WORKER (EXCLUDING HVAC DUCT & SYSTEM INSTALLATION) $42.51 $35.77 $78.28
SUMI2011-074 Effective 02/14/2011
Trade Rate Fringe Total
TRUCK DRIVER: FLATBED TRUCK $16.80 $3.97 $20.77
TRUCK DRIVER, INCLUDES DUMP AND TANDEM TRUCK $15.65 $3.12 $18.77
ROOFER $15.73 $7.41 $23.14
PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION $16.13 $3.67 $19.80
OPERATOR: TRACTOR $19.60 $7.31 $26.91
OPERATOR: ROLLER $28.02 $7.07 $35.09
OPERATOR: GRADER/BLADE $24.04 $6.03 $30.07
OPERATOR: BULLDOZER $22.34 $1.22 $23.56
OPERATOR: BACKHOE/EXCAVATOR $20.34 $14.59 $34.93
LABORER: MASON TENDER - CEMENT/CONCRETE $16.11 $4.51 $20.62
LABORER: LANDSCAPE & IRRIGATION $12.84 $0.00 $12.84
GLAZIER $16.95 $4.74 $21.69
FLOOR LAYER: CARPET $19.59 $7.57 $27.16
CEMENT MASON/CONCRETE FINISHER $19.33 $6.80 $26.13
CARPENTER, EXCLUDES ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION, AND SOFT FLOOR LAYING-CARPET $15.38 $2.31 $17.69
ASBESTOS WORKER/HEAT & FROST INSULATOR $19.82 $7.31 $27.13

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in Michigan.

Get notified when MI20260149 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.