MO20260089

Building

Davis-Bacon Act general wage determination for building construction in Missouri.

Modification 1, revised 05/18/2026 26 trade rates 2 counties View on SAM.gov

Track MO20260089

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0001-001 Effective 10/07/2024
Trade Rate Fringe Total
HEAT & FROST INSULATOR (INCLUDES DUCT, PIPE AND MECHANICAL SYSTEMS) $43.48 $27.24 $70.72
BRMO0001-009 Effective 06/04/2024
Trade Rate Fringe Total
BRICKLAYER $41.15 $23.90 $65.05
BRMO0018-003 Effective 07/05/2023
Trade Rate Fringe Total
TILE SETTER $34.09 $20.36 $54.45
CARP1011-002 Effective 05/01/2024
Trade Rate Fringe Total
CARPENTER $39.78 $22.40 $62.18
CARP1310-002 Effective 05/01/2024
Trade Rate Fringe Total
FLOOR LAYER: SOFT FLOORS $40.08 $21.85 $61.93
ELEC0001-004 Effective 06/22/2025
Trade Rate Fringe Total
ELECTRICIAN (COMMUNICATION TECHNICIAN) $49.29 $33.64 $82.93
ELEC0001-010 Effective 06/22/2025
Trade Rate Fringe Total
ELECTRICIAN $49.29 $33.64 $82.93
ENGI0513-023 Effective 05/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: FORKLIFT $43.46 $30.22 $73.68
POWER EQUIPMENT OPERATOR: BOBCAT/SKID STEER/SKID LOADER $43.46 $30.22 $73.68
POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE $43.46 $30.22 $73.68
ENGI0513-026 Effective 05/01/2025
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: OILER $39.06 $30.38 $69.44
ENGI0513-027 Effective 05/07/2025
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: BULLDOZER $45.96 $30.57 $76.53
ENGI0513-028 Effective 05/07/2025
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: CRANE $45.96 $30.57 $76.53
IRON0396-008 Effective 08/06/2025
Trade Rate Fringe Total
IRONWORKER $44.27 $31.65 $75.92
LABO0110-007 Effective 06/04/2025
Trade Rate Fringe Total
LABORER: PIPELAYER $40.82 $17.56 $58.38
LABO0110-009 Effective 03/01/2025
Trade Rate Fringe Total
LABORER, COMMON OR GENERAL (PROJECTS UNDER 2,000,000) $32.23 $15.91 $48.14
LABORER, COMMON OR GENERAL (PROJECTS OVER $20,000,000) $35.73 $15.91 $51.64
LABORER, COMMON OR GENERAL (PROJECTS BETWEEN $1,000,000 & $20,000,000) $34.23 $15.91 $50.14
LABO1104-007 Effective 03/01/2025
Trade Rate Fringe Total
LABORER: MASON TENDER - CEMENT/CONCRETE $31.80 $14.91 $46.71
PADC0058-001 Effective 09/01/2024
Trade Rate Fringe Total
PAINTER $39.40 $17.66 $57.06
PLAS0527-005 Effective 04/01/2023
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $38.46 $20.15 $58.61
PLUM0562-018 Effective 07/01/2025
Trade Rate Fringe Total
PIPEFITTER $52.60 $29.93 $82.53
PLUM0562-019 Effective 07/01/2025
Trade Rate Fringe Total
PLUMBER $52.60 $29.93 $82.53
ROOF0002-016 Effective 03/01/2025
Trade Rate Fringe Total
ROOFER $40.00 $22.05 $62.05
SFMO0268-005 Effective 01/01/2025
Trade Rate Fringe Total
SPRINKLER FITTER $51.73 $29.55 $81.28
SHEE0036-036 Effective 08/01/2025
Trade Rate Fringe Total
SHEET METAL WORKER $52.00 $27.12 $79.12

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 2 counties in Missouri.

Get notified when MO20260089 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.