OH20260062

Building

Davis-Bacon Act general wage determination for building construction in Ohio.

Modification 1, revised 05/18/2026 33 trade rates 1 county View on SAM.gov

Track OH20260062

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0045-004 Effective 07/01/2024
Trade Rate Fringe Total
ASBESTOS WORKER/HEAT & FROST INSULATOR $37.00 $28.27 $65.27
BROH0022-007 Effective 06/01/2024
Trade Rate Fringe Total
BRICK POINTER/CAULKER/CLEANER $33.30 $18.28 $51.58
CARP0351-001 Effective 05/01/2024
Trade Rate Fringe Total
CARPENTER (EXCLUDING SOFT FLOOR LAYING) $30.45 $24.96 $55.41
CARP0372-005 Effective 05/01/2024
Trade Rate Fringe Total
SOFT FLOOR LAYER $30.25 $25.16 $55.41
ELEC0008-003 Effective 05/27/2024
Trade Rate Fringe Total
ELECTRICIAN $48.40 $25.24 $73.64
ENGI0018-033 Effective 05/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: FORKLIFT $42.98 $16.41 $59.39
POWER EQUIPMENT OPERATOR (BACKHOE/EXCAVATOR/TRACKHOE; CRANE; SCRAPER) $44.14 $16.41 $60.55
IRON0055-013 Effective 07/01/2024
Trade Rate Fringe Total
IRONWORKER, STRUCTURAL $35.50 $29.20 $64.70
IRON0550-009 Effective 05/01/2025
Trade Rate Fringe Total
IRONWORKER: ORNAMENTAL $36.00 $23.57 $59.57
LABO0423-002 Effective 05/01/2021
Trade Rate Fringe Total
LABORER (CHAIN LINK/CYCLONE FENCE ERECTION) $28.73 $11.80 $40.53
LABO0500-004 Effective 05/01/2024
Trade Rate Fringe Total
LABORER (MASON TENDER - CEMENT/CONCRETE) $32.35 $16.42 $48.77
PAIN0948-002 Effective 07/01/2025
Trade Rate Fringe Total
GLAZIER $36.50 $25.06 $61.56
PLAS0886-002 Effective 07/01/2025
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $35.73 $24.65 $60.38
PLUM0050-010 Effective 06/30/2025
Trade Rate Fringe Total
PLUMBER (HVAC PIPE INSTALLATION ONLY) $51.00 $32.56 $83.56
PIPEFITTER (EXCLUDES HVAC PIPE INSTALLATION) $51.00 $32.56 $83.56
ROOF0134-006 Effective 07/01/2021
Trade Rate Fringe Total
ROOFER $29.07 $19.84 $48.91
SHEE0033-017 Effective 07/01/2024
Trade Rate Fringe Total
SHEET METAL WORKER (EXCLUDES HVAC DUCT AND UNIT INSTALLATION) $39.58 $35.15 $74.73
SUOH2012-064 Effective 08/29/2014
Trade Rate Fringe Total
TRUCK DRIVER: DUMP (ALL TYPES) $17.97 $4.14 $22.11
SPRINKLER FITTER (FIRE SPRINKLERS) $25.91 $9.18 $35.09
SHEET METAL WORKER (HVAC DUCT AND HVAC UNIT INSTALLATION ONLY) $22.05 $12.18 $34.23
PLUMBER, EXCLUDES HVAC PIPE INSTALLATION $29.57 $17.20 $46.77
PAINTER (BRUSH AND ROLLER) $17.91 $10.85 $28.76
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) $25.85 $10.42 $36.27
OPERATOR: LOADER $17.43 $2.72 $20.15
OPERATOR: BULLDOZER $23.50 $7.51 $31.01
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $20.00 $3.26 $23.26
LABORER: PIPELAYER $18.37 $4.79 $23.16
LABORER: MASON TENDER - BRICK $22.74 $8.60 $31.34
LABORER: LANDSCAPE & IRRIGATION $10.39 $0.00 $10.39
LABORER: COMMON OR GENERAL $24.76 $9.10 $33.86
DRYWALL HANGER AND METAL STUD INSTALLER $17.63 $5.64 $23.27
DRYWALL FINISHER/TAPER $18.57 $3.12 $21.69
BRICKLAYER $27.47 $12.26 $39.73

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in Ohio.

Get notified when OH20260062 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.