OH20260074

Building

Davis-Bacon Act general wage determination for building construction in Ohio.

Modification 1, revised 05/18/2026 36 trade rates 1 county View on SAM.gov

Track OH20260074

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0003-002 Effective 08/01/2024
Trade Rate Fringe Total
ASBESTOS WORKER/HEAT & FROST INSULATOR $43.88 $26.93 $70.81
BROH0005-006 Effective 05/01/2023
Trade Rate Fringe Total
BRICKLAYER $38.13 $20.19 $58.32
BROH0005-007 Effective 05/01/2023
Trade Rate Fringe Total
BRICK POINTER/CAULKER/CLEANER $38.13 $20.19 $58.32
BROH0005-009 Effective 05/01/2024
Trade Rate Fringe Total
TILE FINISHER $31.50 $16.23 $47.73
BROH0036-001 Effective 05/01/2024
Trade Rate Fringe Total
TILE SETTER $36.07 $19.49 $55.56
CARP0373-001 Effective 05/01/2024
Trade Rate Fringe Total
SOFT FLOOR LAYER $37.52 $23.50 $61.02
CARP0435-004 Effective 05/01/2024
Trade Rate Fringe Total
CARPENTER (INCLUDING DRYWALL HANGING AND METAL STUD INSTALLATION; EXCLUDING SOFT FLOOR LAYING AND FORM WORK) $37.52 $23.50 $61.02
CARP1090-001 Effective 05/01/2025
Trade Rate Fringe Total
PILEDRIVERMAN $36.34 $27.50 $63.84
ELEC0038-005 Effective 04/28/2025
Trade Rate Fringe Total
ELECTRICIAN (LOW VOLTAGE WIRING ONLY) FOOTNOTES; A. 6 PAID HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY; JULY 4TH; LABOR DAY; THANKSGIVING DAY; & CHRISTMAS DAY B. 1 WEEK'S PAID VACATION FOR 1 YEAR'S SERVICE; 2 WEEKS' PAID VACATION FOR 2 OR MORE YEARS' SERVICE $33.05 $14.91 $47.96
ENGI0018-039 Effective 05/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR (OILER) $36.93 $16.41 $53.34
POWER EQUIPMENT OPERATOR (BACKHOE/EXCAVATOR/TRACKHOE; CRANE) $46.71 $16.41 $63.12
ENGI0018-040 Effective 05/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: BULLDOZER $46.71 $16.41 $63.12
ENGI0066-045 Effective 06/01/2017
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: GRADER/BLADE $32.42 $19.66 $52.08
POWER EQUIPMENT OPERATOR: FORKLIFT $28.87 $19.66 $48.53
POWER EQUIPMENT OPERATOR (MECHANIC) $32.92 $19.66 $52.58
IRON0017-011 Effective 05/01/2024
Trade Rate Fringe Total
IRONWORKER (ORNAMENTAL, REINFORCING, & STRUCTURAL) $36.83 $29.01 $65.84
LABO0310-002 Effective 06/01/2024
Trade Rate Fringe Total
LABORER (COMMON OR GENERAL; MASON TENDER - BRICK & CEMENT/CONCRETE) $31.89 $22.66 $54.55
LABO0894-003 Effective 06/01/2018
Trade Rate Fringe Total
LABORER: PIPELAYER $31.27 $10.90 $42.17
LABO0894-004 Effective 05/01/2018
Trade Rate Fringe Total
LABORER (FORM WORK) $32.28 $10.95 $43.23
PAIN0181-001 Effective 05/01/2024
Trade Rate Fringe Total
GLAZIER $34.82 $20.80 $55.62
PAIN0707-002 Effective 05/01/2024
Trade Rate Fringe Total
PAINTER: BRUSH AND ROLLER $32.35 $19.45 $51.80
PAIN0707-003 Effective 05/01/2025
Trade Rate Fringe Total
PAINTER (DRYWALL FINISHING/TAPING ONLY) $35.45 $20.20 $55.65
PLAS0031-018 Effective 05/01/2014
Trade Rate Fringe Total
PLASTERER (INCLUDING FLOOR LAYER: FLOOR COATING/EPOXY) $29.51 $15.67 $45.18
PLAS0404-001 Effective 05/01/2025
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $35.58 $23.71 $59.29
PLUM0055-002 Effective 05/05/2025
Trade Rate Fringe Total
PLUMBER (EXCLUDES HVAC PIPE INSTALLATION) $44.86 $30.03 $74.89
PLUM0120-009 Effective 05/01/2025
Trade Rate Fringe Total
SPRINKLER FITTER (FIRE SPRINKLERS) $49.17 $28.55 $77.72
PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) $49.17 $28.55 $77.72
ROOF0044-003 Effective 04/27/2025
Trade Rate Fringe Total
ROOFER $40.15 $21.28 $61.43
SHEE0033-044 Effective 05/01/2024
Trade Rate Fringe Total
SHEET METAL WORKER (INCLUDING HVAC DUCT AND UNIT INSTALLATION) $43.06 $30.11 $73.17
SUOH2012-076 Effective 08/29/2014
Trade Rate Fringe Total
TRUCK DRIVER: DUMP (ALL TYPES) $24.32 $11.73 $36.05
PAINTER: SPRAY $22.78 $12.40 $35.18
OPERATOR: ROLLER $31.48 $12.80 $44.28
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) $31.48 $12.80 $44.28
OPERATOR: LOADER $29.66 $12.61 $42.27
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $32.88 $12.26 $45.14
LABORER: ASPHALT, INCLUDES RAKER, SHOVELER, SPREADER AND DISTRIBUTOR $24.53 $14.55 $39.08

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in Ohio.

Get notified when OH20260074 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.