WV20260071

Heavy

Davis-Bacon Act general wage determination for heavy construction in West Virginia.

Modification 1, revised 05/18/2026 24 trade rates 1 county View on SAM.gov

Track WV20260071

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

CARP0441-006 Effective 12/01/2020
Trade Rate Fringe Total
CARPENTER, INCLUDES FORM WORK $33.80 $17.61 $51.41
ELEC0596-004 Effective 06/01/2025
Trade Rate Fringe Total
ELECTRICIAN $43.77 $27.72 $71.49
ENGI0132-019 Effective 12/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATOR: GROUP 3 ROLLER $38.08 $20.45 $58.53
POWER EQUIPMENT OPERATOR: GROUP 2 LOADERS UP TO SIX (6) CUBIC YARD CAPACITY, BACKHOE, BULLDOZERS, COMPACTOR, FORKLIFT, GRADER/BLADE, MECHANIC, EXCAVATORS WITH AN OPERATING WEIGHT OF UP TO ONE HUNDRED TEN THOUSAND (110,000) POUNDS, TRACTOR, TRENCHER $39.19 $20.45 $59.64
POWER EQUIPMENT OPERATOR: GROUP 1 CRANES (ALL TYPES, INCLUDING TOWER CRANES), LOADERS OF SIX (6) CUBIC YARD CAPACITY AND OVER, EXCAVATORS WITH AN OPERATING WEIGHT OF ONE HUNDRED TEN THOUSAND (110,000) POUNDS AND OVER $41.95 $20.45 $62.40
IRON0549-012 Effective 12/01/2024
Trade Rate Fringe Total
IRONWORKER, ORNAMENTAL, REINFORCING AND STRUCTURAL $35.50 $29.11 $64.61
LABO0379-049 Effective 12/01/2021
Trade Rate Fringe Total
LABORER: GROUP 2 CARPENTER TENDER, COMMON OR GENERAL, DEMOLITION, FLAGGER $25.26 $16.50 $41.76
LABORER: GROUP 1 BOBCAT OPERATOR (CLEAN UP/DEMOLITION), CHAIN SAW, CONCRETE SAW(HAND HELD/WALK BEHIND), CONCRETE WORKER, HAND HELD DRILL, GRADE CHECKER, WACKER ROLLER OPERATOR $26.32 $16.50 $42.82
LABO1149-012 Effective 12/01/2020
Trade Rate Fringe Total
LABORER: TAMPER (HAND HELD) $26.17 $16.75 $42.92
LABORER: JACK HAMMER $26.17 $16.75 $42.92
LABORER: ASPHALT RAKER $26.17 $16.75 $42.92
PAIN1144-006 Effective 12/01/2024
Trade Rate Fringe Total
PAINTER: SPRAY $34.49 $17.53 $52.02
PLAS0926-001 Effective 12/01/2025
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $35.77 $27.54 $63.31
SUWV2012-069 Effective 08/13/2012
Trade Rate Fringe Total
TRUCK DRIVER, DUMP (EXCLUDING OFF THE ROAD TRUCKS) $23.50 $11.49 $34.99
PIPEFITTER $35.86 $19.30 $55.16
OPERATOR: PAVER (ASPHALT, AGGREGATE, AND CONCRETE) $24.39 $15.50 $39.89
OPERATOR: OILER $22.03 $14.64 $36.67
OPERATOR: BOOM $28.71 $11.59 $40.30
OPERATOR: BOBCAT/SKID STEER/SKID LOADER $24.75 $14.94 $39.69
LABORER: PIPELAYER $18.53 $6.86 $25.39
TEAM0175-008 Effective 12/07/2015
Trade Rate Fringe Total
TRUCK DRIVER: TRACTOR HAUL TRUCK $31.77 $15.98 $47.75
TRUCK DRIVER: PICK-UP TRUCK $30.01 $15.98 $45.99
TRUCK DRIVER: OFF THE ROAD TRUCK $31.77 $15.98 $47.75
TRUCK DRIVER: FLATBED TRUCK $30.98 $15.98 $46.96

Modification History

Modification Publication Date
0 01/02/2026
1 05/18/2026

Counties Covered

This wage determination applies to 1 county in West Virginia.

Get notified when WV20260071 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.