| Save | Trade & Classification | Rate | Fringe | Total |
|---|---|---|---|---|
| ASBESTOS WORKER/HEAT & FROST INSULATOR Building ASBE0076-008 | $36.66 | $11.83 | $48.49 | |
| CARPENTER Residential SUNM1999-003 (EXCLUDING INSTALLATION OF SOFT FLOORS AND BATT AND BLOWN INSULATION) | $10.85 | $0.30 | $11.15 | |
| CARPENTER Building CARP1319-017 | $29.09 | $16.20 | $45.29 | |
| CARPENTER (FORM WORK ONLY) Heavy CARP1319-011 | $27.31 | $13.18 | $40.49 | |
| CARPENTER (INCLUDING FORMWORK AND FRAMING) Residential SUNM1994-001 | $10.00 | 0.00 | $10.00 | |
| CARPENTER, EXCLUDES FORM WORK Heavy SUNM2016-009 | $16.43 | 0.00 | $16.43 | |
| CEMENT MASON/CONCRETE FINISHER Residential SUNM1994-001 Scope differs by code/WD | $8.96 | 0.00 | $8.96 | |
| CEMENT MASON/CONCRETE FINISHER Residential SUNM1999-003 Scope differs by code/WD | $10.91 | 0.00 | $10.91 | |
| CEMENT MASON/CONCRETE FINISHER Heavy SUNM2016-009 | $19.44 | $8.08 | $27.52 | |
| CEMENT MASON/CONCRETE FINISHER Building SUNM2016-003 | $18.93 | $5.85 | $24.78 | |
| DRYWALL FINISHER/TAPER Residential SUNM1999-003 | $8.00 | 0.00 | $8.00 | |
| ELECTRICIAN Residential SUNM1994-001 Scope differs by code/WD | $12.76 | 0.00 | $12.76 | |
| ELECTRICIAN Residential SUNM1999-003 Scope differs by code/WD | $12.00 | $0.23 | $12.23 | |
| ELECTRICIAN Heavy ELEC0611-001 | $34.50 | $10.81 | $45.31 | |
| ELECTRICIAN Building ELEC0611-022 | $40.30 | $13.41 | $53.71 | |
| ELECTRICIAN (BOOM OPERATOR) Highway ELEC0611-003 | $29.79 | $12.74 | $42.53 | |
| FLOOR LAYER: CARPET Residential SUNM1999-003 | $10.00 | 0.00 | $10.00 | |
| FLOOR LAYER: CARPET (CARPET, VINYL, AND LINOLEUM) Residential SUNM1994-001 | $11.00 | 0.00 | $11.00 | |
| INSULATOR (BATT/BLOWN) Residential SUNM1994-001 | $7.25 | 0.00 | $7.25 | |
| IRONWORKER, REINFORCING Heavy SUNM2016-009 | $27.80 | 0.00 | $27.80 | |
| IRONWORKER, STRUCTURAL Building IRON0495-002 | $28.05 | $18.11 | $46.16 | |
| LABORER, GENERAL Residential SUNM1994-001 | $7.25 | 0.00 | $7.25 | |
| LABORER, UNSKILLED Residential SUNM1999-003 | $8.13 | 0.00 | $8.13 | |
| LABORER: COMMON OR GENERAL Heavy SUNM2016-009 | $14.87 | $3.36 | $18.23 | |
| LABORER: COMMON OR GENERAL Building SUNM2016-003 | $13.16 | 0.00 | $13.16 | |
| LABORER: MASON TENDER - CEMENT/CONCRETE Building SUNM2016-003 | $17.60 | 0.00 | $17.60 | |
| LABORER: PIPELAYER Heavy SUNM2016-009 | $16.67 | $3.04 | $19.71 | |
| LATHER Residential SUNM1994-001 | $10.00 | 0.00 | $10.00 | |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE Heavy SUNM2016-009 | $20.85 | $4.19 | $25.04 | |
| OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE Building SUNM2016-003 | $25.73 | $4.51 | $30.24 | |
| OPERATOR: BOBCAT/SKID STEER/SKID LOADER Heavy SUNM2016-009 | $21.06 | 0.00 | $21.06 | |
| OPERATOR: BULLDOZER Heavy SUNM2016-009 | $21.00 | 0.00 | $21.00 | |
| OPERATOR: GRADER/BLADE Heavy SUNM2016-009 | $19.02 | 0.00 | $19.02 | |
| OPERATOR: LOADER Heavy SUNM2016-009 | $18.30 | 0.00 | $18.30 | |
| OPERATOR: OILER Heavy SUNM2016-009 | $18.23 | 0.00 | $18.23 | |
| OPERATOR: ROLLER Heavy SUNM2016-009 | $18.83 | 0.00 | $18.83 | |
| PAINTER (BRUSH AND ROLLER) Building SUNM2016-003 | $16.60 | $3.88 | $20.48 | |
| PAINTER (EXCLUDING DRYWALL FINISHING) Residential SUNM1999-003 | $9.00 | 0.00 | $9.00 | |
| PAINTER, BRUSH, SPRAY AND ROLLER Residential SUNM1994-001 | $8.79 | 0.00 | $8.79 | |
| PAINTER: SPRAY Building SUNM2016-003 | $16.51 | $2.14 | $18.65 | |
| PIPEFITTER (INCLUDES HVAC PIPE INSTALLATION) Building PLUM0412-016 | $43.07 | $16.60 | $59.67 | |
| PLASTERER Residential SUNM1994-001 | $10.00 | 0.00 | $10.00 | |
| PLUMBER Residential SUNM1994-001 | $11.07 | 0.00 | $11.07 | |
| PLUMBER Building PLUM0412-016 | $43.07 | $16.60 | $59.67 | |
| PLUMBER (INCLUDING HVAC WORK) Residential SUNM1999-003 | $16.07 | $0.65 | $16.72 | |
| POWER EQUIPMENT OPERATOR (BACKHOE) Residential SUNM1994-001 | $8.75 | 0.00 | $8.75 | |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (DONA ANA) Highway SUNM2011-003 | $17.74 | $0.26 | $18.00 | |
| POWER EQUIPMENT OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE (SAN JUAN) Highway SUNM2011-003 | $16.27 | $1.51 | $17.78 | |
| POWER EQUIPMENT OPERATOR: BOBCAT/SKID LOADER Highway SUNM2011-003 | $14.56 | $0.26 | $14.82 | |
| POWER EQUIPMENT OPERATOR: CARPENTER, INCLUDES FORM WORK (DONA ANA) Highway SUNM2011-003 | $14.15 | $0.44 | $14.59 | |
| POWER EQUIPMENT OPERATOR: CARPENTER, INCLUDES FORM WORK (SAN JUAN) Highway SUNM2011-003 | $13.42 | $0.44 | $13.86 | |
| POWER EQUIPMENT OPERATOR: CEMENT MASON/CONCRETE FINISHER Highway SUNM2011-003 | $13.65 | $0.26 | $13.91 | |
| POWER EQUIPMENT OPERATOR: ELECTRICIAN, INCLUDES TRAFFIC SIGNALIZATION AND INSTALLATION (DONA ANA) Highway SUNM2011-003 | $25.91 | $9.45 | $35.36 | |
| POWER EQUIPMENT OPERATOR: ELECTRICIAN, INCLUDES TRAFFIC SIGNALIZATION AND INSTALLATION (SAN JUAN) Highway SUNM2011-003 | $24.46 | $8.56 | $33.02 | |
| POWER EQUIPMENT OPERATOR: GRADER/BLADE Highway SUNM2011-003 | $17.64 | $1.51 | $19.15 | |
| POWER EQUIPMENT OPERATOR: HIGHWAY/PARKING LOT STRIPING: INCLUDES HIGHWAY LINE/PARKING LOT LINE STRIPING AND LINE STRIPING TRUCK DRIVER (DONA ANA) Highway SUNM2011-003 | $15.44 | $0.35 | $15.79 | |
| POWER EQUIPMENT OPERATOR: HIGHWAY/PARKING LOT STRIPING: INCLUDES HIGHWAY LINE/PARKING LOT LINE STRIPING AND LINE STRIPING TRUCK DRIVER (SAN JUAN) Highway SUNM2011-003 | $14.39 | $0.35 | $14.74 | |
| POWER EQUIPMENT OPERATOR: IRONWORKER, REINFORCING (DONA ANA) Highway SUNM2011-003 | $22.61 | $6.03 | $28.64 | |
| POWER EQUIPMENT OPERATOR: IRONWORKER, REINFORCING (SAN JUAN) Highway SUNM2011-003 | $16.41 | $5.85 | $22.26 | |
| POWER EQUIPMENT OPERATOR: LABORER (FLAGGER/CONE SETTER) Highway SUNM2011-003 | $14.27 | $0.35 | $14.62 | |
| POWER EQUIPMENT OPERATOR: LABORER, COMMON OR GENERAL (DONA ANA) Highway SUNM2011-003 | $11.95 | $0.35 | $12.30 | |
| POWER EQUIPMENT OPERATOR: LABORER: COMMON OR GENERAL (SAN JUAN) Highway SUNM2011-003 | $11.48 | $0.35 | $11.83 | |
| POWER EQUIPMENT OPERATOR: LABORER: MASON TENDER-CEMENT/CONCRETE Highway SUNM2011-003 | $10.25 | $0.35 | $10.60 | |
| POWER EQUIPMENT OPERATOR: LABORER: PIPELAYER Highway SUNM2011-003 | $17.13 | $5.04 | $22.17 | |
| POWER EQUIPMENT OPERATOR: MECHANIC Highway SUNM2011-003 | $23.24 | $1.51 | $24.75 | |
| POWER EQUIPMENT OPERATOR: OILER Highway SUNM2011-003 | $22.08 | $8.72 | $30.80 | |
| POWER EQUIPMENT OPERATOR: POWER EQUIPMENT OPERATOR: (BROOM SWEEPER) Highway SUNM2011-003 | $16.67 | $1.57 | $18.24 | |
| POWER EQUIPMENT OPERATOR: POWER EQUIPMENT OPERATOR: (LOADER(FRONT END)) Highway SUNM2011-003 | $16.53 | $0.26 | $16.79 | |
| POWER EQUIPMENT OPERATOR: POWER EQUIPMENT OPERATOR: (PILEDRIVER) Highway SUNM2011-003 | $16.26 | $0.26 | $16.52 | |
| POWER EQUIPMENT OPERATOR: ROLLER Highway SUNM2011-003 (ASPHALT AND DIRT) (SAN JUAN) | $12.91 | $1.60 | $14.51 | |
| POWER EQUIPMENT OPERATOR: ROLLER Highway SUNM2011-003 (ASPHALT AND DIRT) (DONA ANA) | $16.27 | $1.51 | $17.78 | |
| POWER EQUIPMENT OPERATOR: TRENCHER (DONA ANA) Highway SUNM2011-003 | $15.22 | $0.26 | $15.48 | |
| POWER EQUIPMENT OPERATOR: TRENCHER (SAN JUAN) Highway SUNM2011-003 | $15.93 | $0.26 | $16.19 | |
| ROOFER Residential SUNM1994-001 Scope differs by code/WD | $8.76 | 0.00 | $8.76 | |
| ROOFER Residential SUNM1999-003 Scope differs by code/WD | $9.87 | 0.00 | $9.87 | |
| SHEET METAL WORKER Residential SUNM1999-003 (SETTING OF HVAC UNIT AND DUCT WORK INSTALLATION ONLY) | $14.43 | $0.58 | $15.01 | |
| SHEET METAL WORKER Building SHEE0049-005 (INCLUDES HVAC DUCT INSTALLATION) | $37.50 | $18.51 | $56.01 | |
| TRUCK DRIVER (FLATBED TRUCK) Highway SUNM2011-003 | $13.30 | $0.26 | $13.56 | |
| TRUCK DRIVER: DUMP (SAN JUAN) Highway TEAM0492-003 | $21.70 | $9.65 | $31.35 | |
| TRUCK DRIVER: DUMP TRUCK Heavy SUNM2016-009 | $15.53 | 0.00 | $15.53 | |
| TRUCK DRIVER: DUMP TRUCK (DONA ANA) Highway SUNM2011-003 | $15.04 | $0.26 | $15.30 | |
| TRUCK DRIVER: PICKUP TRUCK (DONA ANA) Highway SUNM2011-003 | $12.14 | $0.26 | $12.40 | |
| TRUCK DRIVER: PICKUP TRUCK (SAN JUAN) Highway SUNM2011-003 | $12.95 | $0.26 | $13.21 | |
| TRUCK DRIVER: WATER TRUCK Highway SUNM2011-003 | $13.51 | $1.51 | $15.02 |
No trade rates match your search and filter selection.
Residential
Applies to
McKinley, San Juan
Residential
Applies to
Cibola, Colfax, Guadalupe, Harding, McKinley, Mora, Quay, Rio Arriba, San Juan, San Miguel +3 more
Highway
Applies to
Dona Ana, San Juan
Heavy
Building