OK20260005
rev 0Residential
0 trades
Applies to
Adair, Cherokee, Craig, Delaware, Mayes, Nowata, Ottawa, Washington in Oklahoma.
No saved rates yet
Click any row in a trade table to add it here for quick reference.
Click any row to save it for later
| Trade & Classification | Rate | Fringe | Total |
|---|---|---|---|
| Air Conditioning Mechanic Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Asphalt Raker and Shoveler Highway SUOK2011-006 | $12.41 | $0.00 | $12.41 |
| BOILERMAKER Building BOIL0592-001 | $33.70 | $24.41 | $58.11 |
| BRICKLAYER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| BRICKLAYER Building SUOK2012-047 | $20.00 | 0.00 | $20.00 |
| CARPENTER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| CARPENTER Highway SUOK2011-006 (Excludes Form Work and Form Setting) Adair County | $13.70 | $0.00 | $13.70 |
| CARPENTER Building SUOK2012-047 | $13.42 | 0.00 | $13.42 |
| CARPENTER (Form Work Only) Heavy SUOK2012-011 | $14.00 | 0.00 | $14.00 |
| CAULKER Building SUOK2012-047 | $20.00 | $1.61 | $21.61 |
| CEMENT MASON/CONCRETE FINISHER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| CEMENT MASON/CONCRETE FINISHER Building SUOK2012-047 | $16.91 | $0.61 | $17.52 |
| Drywall Installer & Sheetrocker Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| ELECTRICIAN Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| ELECTRICIAN Heavy ELEC1002-005 | $51.00 | $8.75 | $59.75 |
| ELECTRICIAN Building ELEC0584-006 (Excludes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems) | $38.38 | $10.20 | $48.58 |
| ELECTRICIAN Building SUOK2012-047 (Alarm Installation) | $20.47 | $4.52 | $24.99 |
| ELECTRICIAN Building SUOK2012-047 (Low Voltage Wiring) | $21.14 | $4.96 | $26.10 |
| ELECTRICIAN Building SUOK2012-047 (Sound and Communications Systems Installation) | $22.10 | $5.76 | $27.86 |
| ELEVATOR MECHANIC Building ELEV0083-003 | $51.24 | $38.44 | $89.68 |
| FLOOR LAYER: Carpet Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| FORM WORKER/FORM SETTER Highway SUOK2011-006 (Including Curb Line Setting) | $12.30 | $0.00 | $12.30 |
| GUARDRAIL INSTALLER Highway SUOK2011-006 (Includes Guardrail/Post Driver Work) | $9.70 | $0.00 | $9.70 |
| Insulation Installer Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Ironworker Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| IRONWORKER, REINFORCING Highway SUOK2011-006 | $13.63 | $0.00 | $13.63 |
| IRONWORKER, STRUCTURAL Heavy IRON0584-020 | $30.35 | $16.83 | $47.18 |
| IRONWORKER, STRUCTURAL Building IRON0584-010 | $30.35 | $16.83 | $47.18 |
| LABORER Air/Power Tool Operator Highway SUOK2011-006 (Includes Handheld Concrete Saws and Chipping Guns) | $12.79 | $0.00 | $12.79 |
| LABORER Laborers Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| LABORER: Common or General Heavy SUOK2012-011 | $12.41 | 0.00 | $12.41 |
| LABORER: Common or General Building SUOK2012-047 | $11.51 | 0.00 | $11.51 |
| LABORER: Mason Tender - Brick Building SUOK2012-047 | $10.25 | 0.00 | $10.25 |
| LABORER: Mason Tender - Cement/Concrete Building SUOK2012-047 | $13.04 | 0.00 | $13.04 |
| LABORER: Pipelayer Heavy SUOK2012-011 | $13.29 | 0.00 | $13.29 |
| LABORER: Pipelayer Building SUOK2012-047 | $12.93 | 0.00 | $12.93 |
| OPERATOR: Scraper Heavy SUOK2012-011 | $14.00 | 0.00 | $14.00 |
| PAINTER Brush Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| PAINTER: Brush, Roller and Spray Building SUOK2012-047 | $13.56 | 0.00 | $13.56 |
| PIPEFITTER Building PLUM0430-022 (Including HVAC Pipe and Unit Installation) | $36.65 | $16.03 | $52.68 |
| Pipelayer Highway SUOK2011-006 | $11.13 | $0.00 | $11.13 |
| PLUMBER, Excludes HVAC Pipe Installation Building SUOK2012-047 | $24.66 | $10.36 | $35.02 |
| PLUMBER/PIPEFITTER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| POWER EQUIPMENT OPERATOR: Asphalt Paver Screed Highway SUOK2011-006 | $14.77 | $0.00 | $14.77 |
| POWER EQUIPMENT OPERATOR: Asphalt Paving Machine Highway SUOK2011-006 | $14.84 | $0.00 | $14.84 |
| POWER EQUIPMENT OPERATOR: Asphalt Plant Highway SUOK2011-006 | $14.70 | $0.00 | $14.70 |
| POWER EQUIPMENT OPERATOR: Bobcat/Skid Loader Highway SUOK2011-006 | $12.56 | $0.00 | $12.56 |
| POWER EQUIPMENT OPERATOR: Broom Highway SUOK2011-006 | $11.02 | $0.00 | $11.02 |
| POWER EQUIPMENT OPERATOR: Concrete Paving Machine Highway SUOK2011-006 | $14.42 | $0.00 | $14.42 |
| POWER EQUIPMENT OPERATOR: Concrete Saw Highway SUOK2011-006 | $14.65 | $0.00 | $14.65 |
| POWER EQUIPMENT OPERATOR: Crane Highway SUOK2011-006 | $18.63 | $0.00 | $18.63 |
| POWER EQUIPMENT OPERATOR: Distributor Truck Highway SUOK2011-006 | $13.34 | $0.00 | $13.34 |
| POWER EQUIPMENT OPERATOR: Excavator Highway SUOK2011-006 | $14.75 | $0.00 | $14.75 |
| POWER EQUIPMENT OPERATOR: Flatbed Truck Highway SUOK2011-006 | $16.18 | $0.00 | $16.18 |
| POWER EQUIPMENT OPERATOR: Grader/Blade Highway SUOK2011-006 | $16.47 | $0.00 | $16.47 |
| POWER EQUIPMENT OPERATOR: Group 1 Heavy ENGI0627-017 | $38.09 | $19.05 | $57.14 |
| POWER EQUIPMENT OPERATOR: Group 1 Building ENGI0627-022 | $38.09 | $19.05 | $57.14 |
| POWER EQUIPMENT OPERATOR: Group 2 Heavy ENGI0627-017 | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: Group 2 Building ENGI0627-022 | $36.14 | $19.05 | $55.19 |
| POWER EQUIPMENT OPERATOR: Group 3 Heavy ENGI0627-017 | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: Group 3 Building ENGI0627-022 | $35.40 | $19.05 | $54.45 |
| POWER EQUIPMENT OPERATOR: Group 4 Heavy ENGI0627-017 | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: Group 4 Building ENGI0627-022 | $34.07 | $19.05 | $53.12 |
| POWER EQUIPMENT OPERATOR: Group 5 Heavy ENGI0627-017 | $32.71 | $19.05 | $51.76 |
| POWER EQUIPMENT OPERATOR: Group 6 Heavy ENGI0627-017 | $30.87 | $19.05 | $49.92 |
| POWER EQUIPMENT OPERATOR: Group 8 Heavy ENGI0627-017 | $28.77 | $19.05 | $47.82 |
| POWER EQUIPMENT OPERATOR: Group 8 Building ENGI0627-022 | $28.77 | $19.05 | $47.82 |
| POWER EQUIPMENT OPERATOR: Group 9 Heavy ENGI0627-017 | $28.25 | $19.05 | $47.30 |
| POWER EQUIPMENT OPERATOR: Group10 Heavy ENGI0627-017 | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: Group10 Building ENGI0627-022 | $27.25 | $19.05 | $46.30 |
| POWER EQUIPMENT OPERATOR: Loader Highway SUOK2011-006 (Front End) Muskogee County | $13.83 | $0.00 | $13.83 |
| POWER EQUIPMENT OPERATOR: Lowboy/Float Highway SUOK2011-006 | $15.20 | $0.69 | $15.89 |
| POWER EQUIPMENT OPERATOR: Milling Machine Highway SUOK2011-006 | $14.87 | $0.00 | $14.87 |
| POWER EQUIPMENT OPERATOR: Mixer Highway SUOK2011-006 | $14.56 | $0.00 | $14.56 |
| POWER EQUIPMENT OPERATOR: Off the Road Truck Highway SUOK2011-006 | $13.64 | $0.00 | $13.64 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $16.13 | $0.00 | $16.13 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $14.61 | $0.00 | $14.61 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $13.66 | $0.00 | $13.66 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $18.77 | $0.00 | $18.77 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $14.59 | $0.00 | $14.59 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $13.48 | $0.00 | $13.48 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $13.91 | $0.00 | $13.91 |
| POWER EQUIPMENT OPERATOR: Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $15.75 | $0.00 | $15.75 |
| POWER EQUIPMENT OPERATOR: Roller Highway SUOK2011-006 (Asphalt) Adair County | $13.12 | $0.00 | $13.12 |
| POWER EQUIPMENT OPERATOR: Roller (Dirt Compaction) Highway SUOK2011-006 | $12.44 | $0.00 | $12.44 |
| POWER EQUIPMENT OPERATOR: Rotomill Highway SUOK2011-006 | $17.33 | $0.00 | $17.33 |
| POWER EQUIPMENT OPERATOR: Scraper Highway SUOK2011-006 | $14.13 | $0.00 | $14.13 |
| POWER EQUIPMENT OPERATOR: Single Axle Truck Highway SUOK2011-006 (Includes Pilot Car) | $13.15 | $0.00 | $13.15 |
| POWER EQUIPMENT OPERATOR: Straight Truck Highway SUOK2011-006 | $15.92 | $0.00 | $15.92 |
| POWER EQUIPMENT OPERATOR: Striping Machine Highway SUOK2011-006 | $11.54 | $0.00 | $11.54 |
| POWER EQUIPMENT OPERATOR: Tractor/Box Blade Highway SUOK2011-006 | $12.83 | $0.00 | $12.83 |
| POWER EQUIPMENT OPERATOR: Transfer Material Machine Highway SUOK2011-006 | $12.38 | $0.75 | $13.13 |
| POWER EQUIPMENT OPERATOR: Trencher Highway SUOK2011-006 | $14.66 | $0.00 | $14.66 |
| POWER EQUIPMENT OPERATOR: TRUCK DRIVER Concrete Truck Highway SUOK2011-006 | $14.22 | $0.00 | $14.22 |
| POWER EQUIPMENT OPERATOR: Water Truck Highway SUOK2011-006 | $13.44 | $0.00 | $13.44 |
| Power equipment operators: Backhoe Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: Bulldozers Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: Graders Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: ROOFER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: Sheet metal worker Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: TILE SETTER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: Tractors (small) Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: Trenching machine Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Power equipment operators: TRUCK DRIVER Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $13.94 | $0.00 | $13.94 |
| Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $13.70 | $0.00 | $13.70 |
| Remaining Counties Highway SUOK2011-006 Scope differs by code/WD | $10.64 | $0.00 | $10.64 |
| ROOFER Building SUOK2012-047 | $15.00 | $0.29 | $15.29 |
| SHEET METAL WORKER Building SHEE0270-009 (Including HVAC Duct Installation) | $35.49 | $14.60 | $50.09 |
| SPRINKLER FITTER Building SUOK2012-047 (Fire Sprinklers) | $39.95 | $0.38 | $40.33 |
| Tapers and Finishers Residential SUOK1997-001 | $7.25 | $0.00 | $7.25 |
| Traffic Control Highway SUOK2011-006 (Includes Flagger, Setting Up and Moving Cones/Barrels) | $10.28 | $0.00 | $10.28 |
| TRUCK DRIVER Heavy TEAM0516-006 (3) Flatbed Truck | $30.85 | $16.65 | $47.50 |
| Vibrating Plate Highway SUOK2011-006 | $12.70 | $0.00 | $12.70 |
No trade rates match your search and filter selection.
Residential
Applies to
Adair, Cherokee, Craig, Delaware, Mayes, Nowata, Ottawa, Washington in Oklahoma.
Highway
Applies to
Adair, Cherokee, Craig, Delaware, Mayes, McIntosh, Muskogee, Nowata, Okfuskee, Ottawa +1 more
Heavy
Applies to
Adair, Cherokee, Craig, Delaware, Mayes, McIntosh, Muskogee, Nowata, Okfuskee, Ottawa +1 more
Building
Applies to
Adair, Cherokee in Oklahoma.