MI20260089

Building

Davis-Bacon Act general wage determination for building construction in Michigan.

Modification 2, revised 05/18/2026 33 trade rates 1 county View on SAM.gov

Track MI20260089

Get an email when this wage determination gets a new modification.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Wage Rates

Grouped by classification code. Rates shown are base hourly rate plus fringe benefits.

ASBE0047-002 Effective 07/01/2025
Trade Rate Fringe Total
ASBESTOS WORKER/HEAT & FROST INSULATOR $40.00 $23.65 $63.65
BOIL0169-001 Effective 07/01/2025
Trade Rate Fringe Total
BOILERMAKER $43.50 $36.74 $80.24
CARP0706-005 Effective 06/01/2025
Trade Rate Fringe Total
CARPENTER (INCLUDING ACOUSTICAL CEILING INSTALLATION, DRYWALL HANGING, FORM WORK, METAL STUD INSTALLATION & SCAFFOLD BUILDING) $36.46 $23.69 $60.15
CARP0706-006 Effective 06/01/2025
Trade Rate Fringe Total
CARPENTER (FLOOR LAYER - CARPET, RESILIENT & VINYL FLOORING) $35.86 $23.69 $59.55
CARP1102-002 Effective 06/01/2025
Trade Rate Fringe Total
MILLWRIGHT $42.92 $39.13 $82.05
ELEC0948-003 Effective 06/01/2025
Trade Rate Fringe Total
ELECTRICIAN (EXCLUDES ALARM INSTALLATION & LOW VOLTAGE WIRING) $44.83 $26.96 $71.79
ENGI0324-011 Effective 06/01/2023
Trade Rate Fringe Total
OPERATOR: POWER EQUIPMENT: GROUP 6 FORK TRUCK (20' LIFT AND UNDER FOR MASONRY WORK) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $33.71 $25.25 $58.96
OPERATOR: POWER EQUIPMENT: GROUP 5 BOOM TRUCK (NON-SWINGING) FOOTNOTES: CRANE OPERATOR WITH MAIN BOOM AND JIB 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $39.57 $25.25 $64.82
OPERATOR: POWER EQUIPMENT: GROUP 4 BOBCAT/SKID LOADER; BROOM/SWEEPER; FORK TRUCK (OVER 20' LIFT) 300' OR LONGER: $1.50 PER HOUR ABOVE THE GROUP 1 RATE. CRANE OPERATOR WITH MAIN BOOM AND JIB 400' OR LONGER: $3.00 PER HOUR ABOVE THE GROUP 1 RATE. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, FOURTH OF JULY, LABOR DAY, THANKSGIVING DAY AND CHRISTMAS DAY $39.57 $25.25 $64.82
IRON0025-019 Effective 06/01/2025
Trade Rate Fringe Total
IRONWORKER: STRUCTURAL $36.55 $35.93 $72.48
IRONWORKER: REINFORCING $36.55 $33.37 $69.92
IRON0025-022 Effective 06/01/2025
Trade Rate Fringe Total
IRONWORKER: STRUCTURAL (METAL BUILDING ERECTION ONLY) $30.02 $27.43 $57.45
LABO0259-002 Effective 08/01/2025
Trade Rate Fringe Total
LABORER: ASBESTOS ABATEMENT (REMOVAL FROM FLOORS, WALLS & CEILINGS) $39.08 $15.92 $55.00
LABO0334-005 Effective 06/01/2025
Trade Rate Fringe Total
LABORER: LANDSCAPE & IRRIGATION: GROUP 1 LANDSCAPE SPECIALIST, INCLUDING AIR, GAS AND DIESEL EQUIPMENT OPERATOR, LAWN SPRINKLER INSTALLER, SKIDSTEER (OR EQUIVALENT) $29.93 $9.10 $39.03
LABO1075-002 Effective 06/01/2025
Trade Rate Fringe Total
LABORER: COMMON OR GENERAL; GRADE CHECKER; MASON TENDER - BRICK/CEMENT/CONCRETE, PIPELAYER; SANDBLASTER $29.46 $16.10 $45.56
PAIN0826-002 Effective 06/01/2025
Trade Rate Fringe Total
GLAZIER $37.41 $18.99 $56.40
PAIN1052-007 Effective 05/01/2025
Trade Rate Fringe Total
PAINTER: SPRAY (WEST OF HWY. M-53) $31.01 $17.29 $48.30
PAINTER: BRUSH & ROLER (WEST OF HWY. M-53) $32.58 $18.12 $50.70
PAIN1052-011 Effective 06/01/2025
Trade Rate Fringe Total
DRYWALL FINISHER/TAPER: MACHINE WORK (WEST OF HWY. M-53) $27.15 $15.00 $42.15
DRYWALL FINISHER/TAPER: HAND WORK (WEST OF HWY. M-53) $27.15 $15.00 $42.15
DRYWALL FINISHER/TAPER: DRYWALL SANDING (WEST OF HWY. M-53) $33.54 $18.03 $51.57
PAIN1474-004 Effective 06/01/2010
Trade Rate Fringe Total
PAINTER: DRYWALL FINISHING/TAPING (EAST OF HWY. M-53) $23.79 $12.02 $35.81
PAINTER: BRUSH, ROLLER AND SPRAY (EAST OF HWY. M-53) $23.79 $12.02 $35.81
PLAS0016-029 Effective 04/01/2014
Trade Rate Fringe Total
CEMENT MASON/CONCRETE FINISHER $27.77 $12.88 $40.65
PLAS0067-004 Effective 04/01/2014
Trade Rate Fringe Total
PLASTERER $30.63 $14.07 $44.70
PLUM0370-003 Effective 06/01/2025
Trade Rate Fringe Total
PLUMBER, EXCLUDES HVAC PIPE AND UNIT INSTALLATION $46.61 $22.95 $69.56
PIPEFITTER, INCLUDES HVAC PIPE AND UNIT INSTALLATION $46.61 $22.95 $69.56
ROOF0149-005 Effective 06/01/2024
Trade Rate Fringe Total
ROOFER $30.38 $19.97 $50.35
SFMI0669-001 Effective 01/01/2025
Trade Rate Fringe Total
SPRINKLER FITTER (FIRE SPRINKLERS) $41.34 $27.39 $68.73
SHEE0007-007 Effective 05/01/2024
Trade Rate Fringe Total
POWER EQUIPMENT OPERATORS - HAZARDOUS WASTE REMOVAL:, AREA 2: ENGINEER WHEN OPERATING CRANE WITH BOOM AND JIB OR LEADS 220' OR LONGER (AREA 2: LEVEL D WHEN CAPPING LANDFILL) $42.74 $21.53 $64.27
SUMI2011-014 Effective 02/01/2011
Trade Rate Fringe Total
TRUCK DRIVER: TRACTOR HAUL TRUCK $13.57 $1.18 $14.75
IRONWORKER, ORNAMENTAL $18.48 $7.93 $26.41
INSTALLER - OVERHEAD DOOR $27.98 $0.00 $27.98

Modification History

Modification Publication Date
1 01/23/2026
2 05/18/2026

Counties Covered

This wage determination applies to 1 county in Michigan.

Get notified when MI20260089 is modified

This determination has been revised 2 times. We'll email you when a new modification is published.

Free wage alerts plus occasional contractor resources from us and selected partners. Unsubscribe anytime. Privacy.

Data sourced from SAM.gov and updated weekly. This is an unofficial resource — always verify rates against the official wage determination before using them for bidding or compliance.